Agricultural and Biological Engineering
Agricultural and Biological Engineering is an operational data center in West Lafayette, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Coordinates | 40.42185, -86.91655 |
Power and grid
| Nearest high-voltage substation | Purdue University, 138 kV, 700 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Lafayette 230 Substation, 230 kV, 5.4 km away |
| HV substations within 10 km | 24 |
| Utility | Tipmont Rural Elec Member Corp (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | MISO |
| Power plants within 50 km | 993 MW in 18 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 643 g CO₂ per kWh (Indiana, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 44.7%, gas 36.1%, wind 9.4%, solar 6.5%, oil and other fossil 2.8%. Clean power: 16.4% |
| Industrial power price | USD 0.093 per kWh (Indiana, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 10.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.5 °C (2001 to 2025) |
| Cooling degree days | 510 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.97 kWh per m² per day |
| Wind at 50 m | 6.7 m/s average |
| Water stress today | Medium - High (20-40%) (Indiana) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Agricultural and Biological Engineering to the power grid?
The nearest high-voltage substation in OpenStreetMap is Purdue University (138 kV), about 700 m away. The local utility is Tipmont Rural Elec Member Corp, in the MISO balancing area.
How clean is the power for Agricultural and Biological Engineering?
The grid in Indiana emits about 643 g CO₂ per kWh (2025). Largest sources: coal 44.7%, gas 36.1%, wind 9.4%.
Data centers near West Lafayette
- Learning GIS! 203 m
- Wintek Corporation 2.2 km
- Expedient Indianapolis 83.0 km
- ORI.NET Noblesville 87.3 km
- IUPUI Informatics & Communications Technology Complex 96.2 km
- Netrality - Indy Telcom Center - 733 W. Henry 97.1 km
- DataBank Indianapolis (IND1) 97.1 km
- DataBank Indianapolis (IND2) 97.2 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.