Central de internet - Claro/NET
Central de internet - Claro/NET is an operational data center operated by Claro S/A in Itapetininga, Brazil. Our footprint estimate of its power is about 4.8 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Claro S/A |
| Facility power | 4.8 MW (range 2.4 MW to 7.6 MW) Estimate from building footprint, low confidence. Footprint estimate: about 3,977 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 2,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -23.56957, -48.02853 |
Power and grid
| Nearest high-voltage substation | Estação Avançada de Itapetininga, 138 kV, 2.7 km away (CPFL Santa Cruz) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 3 |
| Power plants within 50 km | 3 MW in 1 plant
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 20.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.4 °C (2001 to 2025) |
| Cooling degree days | 1,256 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.85 kWh per m² per day |
| Wind at 50 m | 4 m/s average |
| Water stress today | Low - Medium (10-20%) (Brazil) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Central de internet - Claro/NET use?
We estimate the facility power at about 4.8 MW. Estimate from building footprint, low confidence.
How close is Central de internet - Claro/NET to the power grid?
The nearest high-voltage substation in OpenStreetMap is Estação Avançada de Itapetininga (138 kV), about 2.7 km away.
How clean is the power for Central de internet - Claro/NET?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Who operates Central de internet - Claro/NET?
Claro S/A.
Data centers near Itapetininga
- Central telefônica de Itapetininga 1.0 km
- Central telefônica da Vivo 3.5 km · 0.6 MW
Sources
Correct this page or get the data