Centro de Informática (CPD) is an operational data center in Plano Piloto, Brazil. Our footprint estimate of its power is about 3.5 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 3.5 MW (range 1.8 MW to 5.6 MW) Estimate from building footprint, low confidence. Footprint estimate: about 977 m² building outline x 3 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 1,500 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -15.77275, -47.86577 |
Power and grid
| Nearest high-voltage substation | Subestação 06, 138 kV, 2.1 km away (Neoenergia) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Subestação Brasília Sul, 345 kV, 23.8 km away |
| HV substations within 10 km | 5 |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 22.2 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.9 °C (2001 to 2025) |
| Cooling degree days | 1,608 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.54 kWh per m² per day |
| Wind at 50 m | 4.7 m/s average |
| Water stress today | Low - Medium (10-20%) (Brazil) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Centro de Informática (CPD) use?
We estimate the facility power at about 3.5 MW. Estimate from building footprint, low confidence.
How close is Centro de Informática (CPD) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Subestação 06 (138 kV), about 2.1 km away.
How clean is the power for Centro de Informática (CPD)?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Data centers near Plano Piloto
- PIX Serpro 1.3 km
- Elea BSB1 - Brasília 2.8 km
- Eletronorte Brasilia 3.3 km
- PIX Hilan 3.8 km
- Elea BSB2 - Brasília 5.2 km
- NWI Datacenter Brasília SIG 5.2 km · 48 MW
- BR.Digital Brasília (BSA1) 8.3 km
- Novácia 8.8 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.