Data Center Directory

CSCS Piz Daint

CSCS Piz Daint is an operational AI data center operated by ETH Domain in Sarnen, Switzerland. Its power is about 4.4 MW. Epoch AI estimates about 55 H100-equivalent AI chips (NVIDIA Tesla P100 PCIe 16GB).

Key facts

StatusOperational
OperatorETH Domain
Facility power4.4 MW
Reported (Epoch AI or owner data)
AI compute55 H100-equivalents
AI chipsNVIDIA Tesla P100 PCIe 16GB
Reported (Epoch AI or owner data)
Chip count5,704
Largest reported cluster at this site (Epoch AI).
GPU capacity if all AIabout 1,900 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Coordinates46.80250, 8.23439

Power and grid

Nearest high-voltage substationUnnamed substation, 220 kV, 5.1 km away
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
HV substations within 10 km1
Power plants within 50 km2.2 GW in 52 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity39 g CO₂ per kWh (Switzerland, 2025)
Average of all power made in the area. Ember.
Grid power mixhydro 52.3%, nuclear 29.9%, solar 12.1%, oil and other fossil 1.9%, bioenergy 1.6%. Clean power: 97.7%

Climate and water

Average temperature7.6 °C
NASA POWER, average of 2001 to 2025.
Highest temperature31.7 °C (2001 to 2025)
Cooling degree days60 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.4 kWh per m² per day
Wind at 50 m3.5 m/s average
Water stress todayLow (<10%) (Obwalden)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low (<10%)
Business-as-usual scenario.

GPU clusters at this site

ClusterChipsCountPowerSince
CSCS Piz Daint Phase 1NVIDIA Tesla P100 PCIe 16GB3,0401.8 MW2016-11-01
CSCS Piz Daint Phase 2NVIDIA Tesla P100 PCIe 16GB5,7044.4 MW2017-06-01

Source: Epoch AI GPU Clusters.

Satellite view

Questions

How much power does CSCS Piz Daint use?

Public data puts the facility power at about 4.4 MW. Reported (Epoch AI or owner data).

What chips does CSCS Piz Daint use?

Reported chips: NVIDIA Tesla P100 PCIe 16GB.

How close is CSCS Piz Daint to the power grid?

The nearest high-voltage substation in OpenStreetMap is an unnamed substation (220 kV), about 5.1 km away.

How clean is the power for CSCS Piz Daint?

The grid in Switzerland emits about 39 g CO₂ per kWh (2025). Largest sources: hydro 52.3%, nuclear 29.9%, solar 12.1%.

Who operates CSCS Piz Daint?

ETH Domain.

Data centers near Sarnen

More ETH Domain data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.