株式会社I・TECソリューションズ data center in Tomakomai
株式会社I・TECソリューションズ data center in Tomakomai is an operational data center operated by 株式会社I・TECソリューションズ in Tomakomai, Japan. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | 株式会社I・TECソリューションズ |
| Coordinates | 42.63479, 141.60323 |
| Website | itecsol.jp |
Power and grid
| Nearest high-voltage substation | 苫小牧変電所, 187 kV, 3.8 km away (北海道電力ネットワーク) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 275 kV, 16.6 km away |
| HV substations within 10 km | 3 |
| Power plants within 50 km | 2.2 GW in 13 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 474 g CO₂ per kWh (Japan, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 32.7%, coal 31.8%, solar 10.8%, nuclear 9.2%, hydro 7.2%. Clean power: 33% |
Climate and water
| Average temperature | 7.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 28.6 °C (2001 to 2025) |
| Cooling degree days | 121 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.39 kWh per m² per day |
| Wind at 50 m | 5.8 m/s average |
| Water stress today | Low (<10%) (Hokkaido) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is 株式会社I・TECソリューションズ data center in Tomakomai to the power grid?
The nearest high-voltage substation in OpenStreetMap is 苫小牧変電所 (187 kV), about 3.8 km away.
How clean is the power for 株式会社I・TECソリューションズ data center in Tomakomai?
The grid in Japan emits about 474 g CO₂ per kWh (2025). Largest sources: gas 32.7%, coal 31.8%, solar 10.8%.
Who operates 株式会社I・TECソリューションズ data center in Tomakomai?
株式会社I・TECソリューションズ.
Data centers near Tomakomai
- ほくでん情報テクノロジー株式会社 data center in Sapporo 51.4 km
- 株式会社HBA data center in Sapporo 51.7 km
- Sakura's H100s 64.2 km · 2.9 MW
- HAMANASU INFORMATION CENTER 64.5 km
- さくらインターネット株式会社 石狩データセンター 65.2 km · 9.6 MW
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.