NEGMA Datacenter
NEGMA Datacenter is an operational data center operated by NEGMA Business Solutions in Farmers Branch, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | NEGMA Business Solutions |
| Address | 4215 N. Beltwood Parkway |
| Coordinates | 32.94958, -96.83735 |
| Website | negma.net |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 138 kV, 500 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | West Plano Substation, 345 kV, 9 km away |
| HV substations within 10 km | 40 |
| Utility | Hilco Electric Cooperative, INC. (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | ERCO |
| Nearest gas pipeline | Atmos Pipeline - Texas, intrastate pipeline, 8.3 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 5.9 GW in 18 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 379 g CO₂ per kWh (Texas, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8% |
| Industrial power price | USD 0.072 per kWh (Texas, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 18.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 45.3 °C (2001 to 2025) |
| Cooling degree days | 1,559 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.64 kWh per m² per day |
| Wind at 50 m | 6.5 m/s average |
| Water stress today | High (40-80%) (Texas) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is NEGMA Datacenter to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (138 kV), about 500 m away. The local utility is Hilco Electric Cooperative, INC., in the ERCO balancing area.
How clean is the power for NEGMA Datacenter?
The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.
Who operates NEGMA Datacenter?
NEGMA Business Solutions.
Data centers near Farmers Branch
- Digital Realty IAD 39 (44274 Round Table) 1.8 km
- Foremost Dallas 3.2 km
- Digital Realty DFW (2440 Marsh Lane) 3.7 km
- DataBank Dallas (DFW7) 5.2 km
- Centersquare Dallas (DFW3) 5.4 km
- Digital Realty DFW (4025 Midway Road) 8.0 km
- Flexential - Dallas/Richardson (RCH01) 9.0 km
- Flexential Dallas - Richardson 9.4 km · 23 MW
Sources