ODATA DC SP01
ODATA DC SP01 is an operational data center in Santana de Parnaíba, Brazil. Our footprint estimate of its power is about 2.7 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 2.7 MW (range 1.1 MW to 6.8 MW) Estimate from building footprint, low confidence. Footprint estimate: about 22,632 m² site outline x 0.12 kW per m² of land. |
| GPU capacity if all AI | about 1,200 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Estrada dos Romeiros |
| Coordinates | -23.45502, -46.91505 |
| Website | odatacolocation.com/en/blog/data-center/dc-sp01 |
Power and grid
| Nearest high-voltage substation | Subestação UHE Edgard de Souza, 230 kV, 800 m away (CTEEP) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 1 |
| Power plants within 50 km | 693 MW in 7 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 19.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.6 °C (2001 to 2025) |
| Cooling degree days | 955 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.53 kWh per m² per day |
| Wind at 50 m | 5 m/s average |
| Water stress today | Low - Medium (10-20%) (Brazil) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does ODATA DC SP01 use?
We estimate the facility power at about 2.7 MW. Estimate from building footprint, low confidence.
How close is ODATA DC SP01 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Subestação UHE Edgard de Souza (230 kV), about 800 m away.
How clean is the power for ODATA DC SP01?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Data centers near Santana de Parnaíba
- Equinix SP3 - São Paulo 5.4 km
- Equinix SP6 - São Paulo 5.7 km
- Equinix SP6 5.9 km · 127 MW
- Scala Data Centers HQ 8.4 km
- Elea SPO3 - Tamboré 8.6 km
- Omid Solutions Barueri 9.1 km
- Equinix SP2 - São Paulo 10.4 km
- Scala Data Centers SGRUTB04 11.2 km
Sources