Orbit Telekom Datacenter is an operational data center operated by Orbit Telekom Sanayi ve Ticaret Limited Sirketi in Isparta Merkez, Türkiye. No power figure is public for this site yet.

Key facts

StatusOperational
OperatorOrbit Telekom Sanayi ve Ticaret Limited Sirketi
Networks1 networks
PeeringDB.
AddressIşıkkent Mah.
Coordinates37.76633, 30.52670
Websiteorbittelekom.com

Power and grid

Nearest high-voltage substationIsparta TM, 154 kV, 12.6 km away (TEİAŞ)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Power plants within 50 km66 MW in 6 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity476 g CO₂ per kWh (Türkiye, 2025)
Average of all power made in the area. Ember.
Grid power mixcoal 34.3%, gas 22.1%, hydro 16.2%, wind 11.1%, solar 10.5%. Clean power: 43.3%
Industrial power priceEUR 0.054 per kWh (Türkiye, 2026-S1)
Non-household users with 20 to 70 GWh per year, without VAT. Eurostat.

Climate and water

Average temperature11.5 °C
NASA POWER, average of 2001 to 2025.
Highest temperature37.3 °C (2001 to 2025)
Cooling degree days404 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.77 kWh per m² per day
Wind at 50 m4 m/s average
Water stress todayExtremely High (>80%) (Isparta)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Extremely High (>80%)
Business-as-usual scenario.

Satellite view

Questions

How close is Orbit Telekom Datacenter to the power grid?

The nearest high-voltage substation in OpenStreetMap is Isparta TM (154 kV), about 12.6 km away.

How clean is the power for Orbit Telekom Datacenter?

The grid in Türkiye emits about 476 g CO₂ per kWh (2025). Largest sources: coal 34.3%, gas 22.1%, hydro 16.2%.

Who operates Orbit Telekom Datacenter?

Orbit Telekom Sanayi ve Ticaret Limited Sirketi.

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.