Poznan Supercomputing and Networking Center
Poznan Supercomputing and Networking Center is an operational data center operated by Poznan Supercomputing and Networking Center in Poznan, Poland. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Poznan Supercomputing and Networking Center |
| Networks | 9 networks, 2 internet exchanges PeeringDB. |
| Address | ul. Noskowskiego 12/14 |
| Coordinates | 52.41183, 16.91625 |
| Website | pcss.pl |
Power and grid
| Nearest high-voltage substation | Stacja elektroenergetyczna 110/15kV "Jeżyce", 110 kV, 900 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Stacja elektroenergetyczna "Czerwonak" 220/110 kV, 220 kV, 8.1 km away |
| HV substations within 10 km | 30 |
| Power plants within 50 km | 321 MW in 4 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 591 g CO₂ per kWh (Poland, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 50.6%, gas 14.4%, wind 13.9%, solar 11.3%, bioenergy 4.9%. Clean power: 31.2% |
| Industrial power price | EUR 0.169 per kWh (Poland, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 9.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37 °C (2001 to 2025) |
| Cooling degree days | 172 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.94 kWh per m² per day |
| Wind at 50 m | 6.5 m/s average |
| Water stress today | Low - Medium (10-20%) (Poland) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Poznan Supercomputing and Networking Center to the power grid?
The nearest high-voltage substation in OpenStreetMap is Stacja elektroenergetyczna 110/15kV "Jeżyce" (110 kV), about 900 m away.
How clean is the power for Poznan Supercomputing and Networking Center?
The grid in Poland emits about 591 g CO₂ per kWh (2025). Largest sources: coal 50.6%, gas 14.4%, wind 13.9%.
Who operates Poznan Supercomputing and Networking Center?
Poznan Supercomputing and Networking Center.
Data centers near Poznan
- St.Dominic Monastery 307 m
- Netia Poznań (POZNH003) 772 m
- Orange Polska // Poznań 962 m
- PCSS Poznan Proxima 1.1 km · 0.5 MW
- Beyond.pl - DC1 / Poznan 1.4 km
- Data center in Poznań 2.6 km · 6.3 MW
- Talex 4.6 km
- Systemia.pl Sp. z o.o. 4.6 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.