SoftBank CHIE-2
SoftBank CHIE-2 is an operational AI data center operated by Softbank in Karuizawa, Japan. Its power is about 2.9 MW. Epoch AI estimates about 2,040 H100-equivalent AI chips (PEZY-SC2, NVIDIA Tesla V100 SXM2, NVIDIA V100, NVIDIA A100, NVIDIA A100 SXM4 80 GB, NVIDIA H100 SXM5 80GB, NVIDIA GH200).
Key facts
| Status | Operational |
|---|---|
| Operator | Softbank |
| Facility power | 2.9 MW Reported (Epoch AI or owner data) |
| AI compute | 2,040 H100-equivalents |
| AI chips | PEZY-SC2, NVIDIA Tesla V100 SXM2, NVIDIA V100, NVIDIA A100, NVIDIA A100 SXM4 80 GB, NVIDIA H100 SXM5 80GB, NVIDIA GH200 Reported (Epoch AI or owner data) |
| Chip count | 10,000 Largest reported cluster at this site (Epoch AI). |
| GPU capacity if all AI | about 1,200 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Japan |
| Coordinates | 36.38649, 138.59223 |
Power and grid
| Nearest high-voltage substation | 佐久変電所, 275 kV, 23.2 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Power plants within 50 km | 1.4 GW in 24 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 474 g CO₂ per kWh (Japan, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 32.7%, coal 31.8%, solar 10.8%, nuclear 9.2%, hydro 7.2%. Clean power: 33% |
Climate and water
| Average temperature | 8.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 30.3 °C (2001 to 2025) |
| Cooling degree days | 212 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.79 kWh per m² per day |
| Wind at 50 m | 4.5 m/s average |
| Water stress today | Low - Medium (10-20%) (Nagano) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
GPU clusters at this site
| Cluster | Chips | Count | Power | Since |
|---|---|---|---|---|
| JAMSTEC ZettaScaler-2.0 Gyoukou | PEZY-SC2 | 1,600 | 0.3 MW | 2017-06-15 |
| JAMSTEC ZettaScaler-2.2 Gyoukou | PEZY-SC2 | 10,000 | 2.6 MW | 2017-11-15 |
| Japanese Research Institute 1 Supercomputer 1 | NVIDIA Tesla V100 SXM2 | 832 | 0.6 MW | 2019-06-01 |
| SAKURA Internet 2019 V100 Supercomputer | NVIDIA Tesla V100 SXM2 | 768 | 0.5 MW | 2019-06-01 |
| Preferred Networks MN-2 | NVIDIA V100 | 1,024 | 0.7 MW | 2019-07-30 |
| Japan Atomic Energy Agency and Quantum and Radiological Science and Technology HPE SGI8600 | NVIDIA Tesla V100 SXM2 | 1,088 | 0.7 MW | 2020-11-01 |
| Japanese Research Institute 2 Supercomputer 1 | NVIDIA A100 | 624 | 0.5 MW | 2022-06-01 |
| NEC Corp Japan Supercomputer | NVIDIA A100 SXM4 80 GB | 928 | 0.8 MW | 2023-07-24 |
| Softbank SuperPOD | NVIDIA A100 | 2,048 | 1.7 MW | 2023-09-30 |
| SoftBank CHIE-2 | NVIDIA H100 SXM5 80GB | 2,040 | 2.9 MW | 2024-10-31 |
| SoftBank CHIE-3 | NVIDIA H100 SXM5 80GB | 2,040 | 2.9 MW | 2024-10-31 |
| JCAHPC Miyabi | NVIDIA GH200 | 1,120 | 1.6 MW | 2025-01-15 |
Source: Epoch AI GPU Clusters.
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does SoftBank CHIE-2 use?
Public data puts the facility power at about 2.9 MW. Reported (Epoch AI or owner data).
What chips does SoftBank CHIE-2 use?
Reported chips: PEZY-SC2, NVIDIA Tesla V100 SXM2, NVIDIA V100, NVIDIA A100, NVIDIA A100 SXM4 80 GB, NVIDIA H100 SXM5 80GB, NVIDIA GH200.
How close is SoftBank CHIE-2 to the power grid?
The nearest high-voltage substation in OpenStreetMap is 佐久変電所 (275 kV), about 23.2 km away.
How clean is the power for SoftBank CHIE-2?
The grid in Japan emits about 474 g CO₂ per kWh (2025). Largest sources: gas 32.7%, coal 31.8%, solar 10.8%.
Who operates SoftBank CHIE-2?
Softbank.
Data centers near Karuizawa
- 電算 data center in Nagano 45.4 km
- 東日本電信電話株式会社 data center in Nagano 45.4 km
- 電算 data center in Nagano 47.2 km
- NTT東日本 小曽木電話交換局 87.7 km
- 2B棟 92.9 km · 56 MW
- NTT武蔵村山電話交換局 99.3 km · 1.6 MW
- NTT 110.8 km
- 野村総合研究所 東京第一DC 112.5 km · 16 MW
More Softbank data centers
- OpenAI Stargate Milam United States
- OpenAI Stargate Lordstown United States
Sources
- Epoch AI, GPU Clusters
- JAMSTEC ZettaScaler-2.0 Gyoukou
- Japanese Research Institute 1 Supercomputer 1
- SAKURA Internet 2019 V100 Supercomputer
- Preferred Networks MN-2
- Japan Atomic Energy Agency and Quantum and Radiological Science and Technology HPE SGI8600
- Japanese Research Institute 2 Supercomputer 1
- NEC Corp Japan Supercomputer
- Softbank SuperPOD
- SoftBank CHIE-2
- SoftBank CHIE-3
- JCAHPC Miyabi
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.