有孚深圳宝安云计算数据中心 is an operational data center operated by 有孚 in Taohuayuan, China. Our footprint estimate of its power is about 4.7 MW.

Key facts

StatusOperational
Operator有孚
Facility power4.7 MW (range 2.3 MW to 7.4 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 3,879 m² building outline x 1 floor(s) x 1.2 kW/m².
GPU capacity if all AIabout 2,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Coordinates22.66353, 113.91726

Power and grid

Grid carbon intensity528 g CO₂ per kWh (China, 2025)
Average of all power made in the area. Ember.
Grid power mixcoal 54.8%, hydro 13.3%, solar 11.2%, wind 10.7%, nuclear 4.6%. Clean power: 41.1%

Climate and water

Average temperature23.5 °C
NASA POWER, average of 2001 to 2025.
Highest temperature34.2 °C (2001 to 2025)
Cooling degree days2,136 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.14 kWh per m² per day
Wind at 50 m5.6 m/s average
Water stress todayLow - Medium (10-20%) (Guangdong)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How much power does 有孚深圳宝安云计算数据中心 use?

We estimate the facility power at about 4.7 MW. Estimate from building footprint, low confidence.

How clean is the power for 有孚深圳宝安云计算数据中心?

The grid in China emits about 528 g CO₂ per kWh (2025). Largest sources: coal 54.8%, hydro 13.3%, solar 11.2%.