Umbrellar CHC1
Umbrellar CHC1 is an operational data center operated by Umbrellar Platform in Christchurch, New Zealand. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Umbrellar Platform |
| Networks | 2 networks PeeringDB. |
| Address | Unit 5, 7 Sir Gil Simpson Drive, Burnside |
| Coordinates | -43.49203, 172.55949 |
| Website | umbrellar.nz |
Power and grid
| Nearest high-voltage substation | Islington Substation, 220 kV, 6.3 km away (Transpower New Zealand) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 1 |
| Power plants within 50 km | 155 MW in 2 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 96 g CO₂ per kWh (New Zealand, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 53.7%, other renewables 22%, wind 9.5%, gas 8.6%, solar 1.8%. Clean power: 88.2% |
Climate and water
| Average temperature | 11.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.3 °C (2001 to 2025) |
| Cooling degree days | 79 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.95 kWh per m² per day |
| Wind at 50 m | 6.3 m/s average |
| Water stress today | Low (<10%) (Canterbury) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Umbrellar CHC1 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Islington Substation (220 kV), about 6.3 km away.
How clean is the power for Umbrellar CHC1?
The grid in New Zealand emits about 96 g CO₂ per kWh (2025). Largest sources: hydro 53.7%, other renewables 22%, wind 9.5%.
Who operates Umbrellar CHC1?
Umbrellar Platform.
Data centers near Christchurch
- Spark Data Centre 1.1 km · 2.2 MW
- HP Secure 1.8 km · 4.2 MW
- Chorus Avonhead Exchange (AVO) 3.7 km
- Enable Networks Hornby POI 5.2 km
- Revera Show Place 6.6 km
- Enable Networks Riccarton POI 6.8 km
- Datacom - Gloucester Data Centre (Christchurch) 7.2 km
- Vetta CH01 7.6 km
More Umbrellar Platform data centers
- Umbrellar AKL1 New Zealand
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.