Blönduós
Blönduós is an operational data center operated by Borealis in Sauðárkrókur, Iceland. Our footprint estimate of its power is about 21 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Borealis |
| Facility power | 21 MW (range 10 MW to 33 MW) Estimate from building footprint, low confidence. Footprint estimate: about 17,159 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 9,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 65.64728, -20.24300 |
| Website | bdc.is/bl%C3%B6ndu%C3%B3s-campus |
Power and grid
| Nearest high-voltage substation | Hnjúkar, 132 kV, 100 m away (Landsnet) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 2 |
| Power plants within 50 km | 150 MW in 1 plant
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 28 g CO₂ per kWh (Iceland, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 71.2%, other renewables 28.7%. Clean power: 100% |
| Industrial power price | EUR 0.090 per kWh (Iceland, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 1.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 22.7 °C (2001 to 2025) |
| Cooling degree days | 0 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.28 kWh per m² per day |
| Wind at 50 m | 7.2 m/s average |
| Water stress today | Low (<10%) (Iceland) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Blönduós use?
We estimate the facility power at about 21 MW. Estimate from building footprint, low confidence.
How close is Blönduós to the power grid?
The nearest high-voltage substation in OpenStreetMap is Hnjúkar (132 kV), about 100 m away.
How clean is the power for Blönduós?
The grid in Iceland emits about 28 g CO₂ per kWh (2025). Largest sources: hydro 71.2%, other renewables 28.7%.
Who operates Blönduós?
Borealis.
Data centers near Sauðárkrókur
- Blönduós Campus 79 m
More Borealis data centers
- Reykjavík DC Iceland
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.