Reykjavík DC is an operational data center operated by Borealis in Reykjavík, Iceland. Our footprint estimate of its power is about 2.9 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Borealis |
| Facility power | 2.9 MW (range 1.4 MW to 4.6 MW) Estimate from building footprint, low confidence. Footprint estimate: about 2,409 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 1,200 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Blikastaðavegur 8, 112, Reykjavík |
| Opened | 2021 |
| Coordinates | 64.14554, -21.75346 |
Power and grid
| Grid carbon intensity | 28 g CO₂ per kWh (Iceland, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | hydro 71.2%, other renewables 28.7%. Clean power: 100% |
| Industrial power price | EUR 0.090 per kWh (Iceland, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 4.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 22.8 °C (2001 to 2025) |
| Cooling degree days | 0 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.26 kWh per m² per day |
| Wind at 50 m | 7.1 m/s average |
| Water stress today | Low (<10%) (Iceland) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Reykjavík DC use?
We estimate the facility power at about 2.9 MW. Estimate from building footprint, low confidence.
How clean is the power for Reykjavík DC?
The grid in Iceland emits about 28 g CO₂ per kWh (2025). Largest sources: hydro 71.2%, other renewables 28.7%.
Who operates Reykjavík DC?
Borealis.
Data centers near Reykjavík
- Reykjavik DC 145 m
- Reykjavík Campus 206 m
- Ármúli 25 6.0 km
- RIX-MH 6.0 km
- Borealis Data Center 6.5 km
- RIX-K2 7.5 km
- RIX-TG 9.8 km
- SDC Capital 10.1 km
More Borealis data centers
- Blönduós Iceland
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.