CapitaLand 9 Tai Seng
CapitaLand 9 Tai Seng is an operational data center operated by CapitaLand Digital in Singapore, Singapore. Our footprint estimate of its power is about 41 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | CapitaLand Digital |
| Facility power | 41 MW (range 20 MW to 65 MW) Estimate from building footprint, low confidence. Footprint estimate: about 5,664 m² building outline x 6 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 18,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | Starhub Data Center @ Tai Seng · Cyxtera Singapore Data Center Campus SIN1 |
| Address | 9 Tai Seng Drive, #01-01 |
| Coordinates | 1.33877, 103.89383 |
| Website | capitaland.com/sg/en/lease/businesspark-industrial-logistics-listing/9-tai-seng-drive.html |
Power and grid
| Nearest high-voltage substation | Paya Lebar 400kV, 400 kV, 800 m away (SPPG) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 5 |
| Power plants within 50 km | 19 GW in 38 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 497 g CO₂ per kWh (Singapore, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 91.1%, bioenergy 2.8%, solar 2.7%, oil and other fossil 2.5%, coal 0.9%. Clean power: 5.5% |
Climate and water
| Average temperature | 27.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 33.9 °C (2001 to 2025) |
| Cooling degree days | 3,296 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.82 kWh per m² per day |
| Wind at 50 m | 4 m/s average |
| Water stress today | NoData (Singapore) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does CapitaLand 9 Tai Seng use?
We estimate the facility power at about 41 MW. Estimate from building footprint, low confidence.
How close is CapitaLand 9 Tai Seng to the power grid?
The nearest high-voltage substation in OpenStreetMap is Paya Lebar 400kV (400 kV), about 800 m away.
How clean is the power for CapitaLand 9 Tai Seng?
The grid in Singapore emits about 497 g CO₂ per kWh (2025). Largest sources: gas 91.1%, bioenergy 2.8%, solar 2.7%.
Who operates CapitaLand 9 Tai Seng?
CapitaLand Digital.
Data centers near Singapore
- Equinix SG4 - Singapore 69 m · 32 MW
- China Mobile International - Singapore DC 197 m · 29 MW
- Racks Central 208 m · 18 MW
- Global Switch Singapore 228 m · 44 MW
- Singtel Kim Chuan Telecommunications Centre 431 m
- STTGDC SIN5 551 m · 6.5 MW
- CapitaLand data center in Singapore 579 m · 40 MW
- STTGDC SIN1 1.2 km · 1.9 MW
More CapitaLand Digital data centers
- Croydon United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.