Cronomagic Canada Inc
Cronomagic Canada Inc is an operational data center operated by Cronomagic in Montreal, Canada. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Cronomagic |
| Networks | 1 networks PeeringDB. |
| Address | 3333 Graham 700 |
| Coordinates | 45.50893, -73.66144 |
| Website | cronomagic.com |
Power and grid
| Nearest high-voltage substation | Poste de Mont-Royal, 120 kV, 1.6 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Poste Fleury, 315 kV, 3.3 km away |
| HV substations within 10 km | 28 |
| Power plants within 50 km | 2.1 GW in 7 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 192 g CO₂ per kWh (Canada, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.8%, gas 19.7%, nuclear 12.8%, wind 8%, coal 2.7%. Clean power: 76.5% |
Climate and water
| Average temperature | 6.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 36.6 °C (2001 to 2025) |
| Cooling degree days | 272 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.54 kWh per m² per day |
| Wind at 50 m | 6.2 m/s average |
| Water stress today | Low - Medium (10-20%) (Canada) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Cronomagic Canada Inc to the power grid?
The nearest high-voltage substation in OpenStreetMap is Poste de Mont-Royal (120 kV), about 1.6 km away.
How clean is the power for Cronomagic Canada Inc?
The grid in Canada emits about 192 g CO₂ per kWh (2025). Largest sources: hydro 52.8%, gas 19.7%, nuclear 12.8%.
Who operates Cronomagic Canada Inc?
Cronomagic.
Data centers near Montreal
- Enovum Datacenters MTL01 2.1 km
- Vidéotron data center in Rosemont–La Petite-Patrie 4.5 km · 3.8 MW
- Bell Canada data center in Rosemont–La Petite-Patrie 4.9 km · 3.2 MW
- eStruxture MTL-2 6.1 km
- Equinix MT1 - Montreal 6.9 km
- Openface DC2 7.0 km
- Cologix MTL12 7.0 km
- Cologix MTL3 7.2 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.