Datacenter The Factory Roermond
Datacenter The Factory Roermond is an operational data center operated by FACTORY in Roermond, Netherlands. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | FACTORY |
| Address | Westhoven 6c |
| Coordinates | 51.19327, 6.01987 |
| Website | factory.nl |
Power and grid
| Nearest high-voltage substation | 150 kV Maalbroek, 150 kV, 2.4 km away (TenneT) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Vernieuwing hoogspanningsstation Maasbracht, 380 kV, 8.5 km away |
| HV substations within 10 km | 15 |
| Power plants within 50 km | 7.7 GW in 71 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 254 g CO₂ per kWh (Netherlands, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 34.9%, wind 25%, solar 21.1%, coal 7.1%, bioenergy 5.1%. Clean power: 54.2% |
| Industrial power price | EUR 0.139 per kWh (Netherlands, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.6 °C (2001 to 2025) |
| Cooling degree days | 131 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.96 kWh per m² per day |
| Wind at 50 m | 6.7 m/s average |
| Water stress today | High (40-80%) (Limburg) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Datacenter The Factory Roermond to the power grid?
The nearest high-voltage substation in OpenStreetMap is 150 kV Maalbroek (150 kV), about 2.4 km away.
How clean is the power for Datacenter The Factory Roermond?
The grid in Netherlands emits about 254 g CO₂ per kWh (2025). Largest sources: gas 34.9%, wind 25%, solar 21.1%.
Who operates Datacenter The Factory Roermond?
FACTORY.
Data centers near Roermond
- Data center in Roermond 2.1 km · 2.3 MW
- ILA/Regeneration site PoP-Maasbracht 9.1 km
- Systemec Venlo DC19 22.7 km
- ZeroPlex DC01 24.9 km
- Unilogic Networks Datacenter Sittard 25.1 km
- Penta Infra Geleen GLN01 27.3 km
- Rechenzentrum Hartmann GmbH & Co. KG 30.1 km · 1.9 MW
- SkyLink Data Center BV 33.3 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.