DC1-Stavanger
DC1-Stavanger is an operational data center operated by Green Mountain in Rennesøy, Norway. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Green Mountain |
| Networks | 11 networks, 1 internet exchanges PeeringDB. |
| Address | Hodneveien 240 |
| Coordinates | 59.07268, 5.76306 |
| Website | greenmountain.no |
Power and grid
| Nearest high-voltage substation | Nye Veland transformatorstasjon, 132 kV, 14.5 km away (Lnett) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 300 kV, 17 km away |
| Power plants within 50 km | 154 MW in 10 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 28 g CO₂ per kWh (Norway, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 89.9%, wind 8.4%, gas 0.6%. Clean power: 99% |
| Industrial power price | EUR 0.097 per kWh (Norway, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 4.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 26.6 °C (2001 to 2025) |
| Cooling degree days | 4 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.43 kWh per m² per day |
| Wind at 50 m | 5.9 m/s average |
| Water stress today | Low (<10%) (Rogaland) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is DC1-Stavanger to the power grid?
The nearest high-voltage substation in OpenStreetMap is Nye Veland transformatorstasjon (132 kV), about 14.5 km away.
How clean is the power for DC1-Stavanger?
The grid in Norway emits about 28 g CO₂ per kWh (2025). Largest sources: hydro 89.9%, wind 8.4%, gas 0.6%.
Who operates DC1-Stavanger?
Green Mountain.
Data centers near Rennesøy
- GC-FAB7 Stavanger 19.9 km
- Maan Group 25.5 km
- EMP Secure DC1 44.9 km
- EMP Secure DC2 45.0 km
More Green Mountain data centers
- Green Mountain Innlandet Norway
- DC3-Oslo Norway
- DC2-Telemark Norway
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.