EcoDataCenter 2
EcoDataCenter 2 is a data center under construction operated by Mistral AI in Borlänge, Sweden. No power figure is public for this site yet.
Power demand is growing at this site
Key facts
| Status | Under construction |
|---|---|
| Operator | Mistral AI |
| Users | Mistral AI |
| Planned power | 67 MW by 2028-06-30 Epoch AI timeline projection. |
| Address | Kvarnsvedsvägen 420, 784 66 Borlänge, Sweden |
| Coordinates | 60.52514, 15.41381 |
Power and grid
| Grid carbon intensity | 36 g CO₂ per kWh (Sweden, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | hydro 40%, nuclear 27.4%, wind 22.8%, bioenergy 5.9%, solar 2.6%. Clean power: 98.7% |
| Industrial power price | EUR 0.096 per kWh (Sweden, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 4.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 30.1 °C (2001 to 2025) |
| Cooling degree days | 23 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.57 kWh per m² per day |
| Wind at 50 m | 4 m/s average |
| Water stress today | Low (<10%) (Dalarna) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2025-09-01 | 0 | 0 | Land clearing begins. [EcoDataCenter](https://ecodatacenter.tech/press/ecodatacenter-breaks-ground-on-mega-campus-in-borlnge-3406556) announces on September 24th that construction has started on EcoDataCenter 2, so we model it as started from the beginning of the month. |
| 2026-05-09 | 0 | 0 | Buildings 1 and 2 still under construction. The first two building shells are visibly well into construction, with lots of additional ground work visible all across the campus. Based on high-resolution satellite imagery from this date. |
| 2026-08-17 | 0 | 0 | Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed. Buildings 3-4 look like their foundations have been laid out and are early in construction. |
| 2027-06-30 (projected) | 34 MW | 69,000 | Buildings 1-2 operational. Based on [Bravida](https://www.bravida.se/en/press/press-releases/2026/bravida-carries-out-installations-in-two-data-centres-for-around-sek-200-million/) stating that installation work in two EcoDataCenter data centers in Borlänge is expected to be completed by mid-2027, together with [EcoDataCenter Annual Report 2025](https://ecodatacenter.tech/hubfs/Annual%20Report%202025_EcoDC%20Holding%20AB_ENG.pdf) identifying B1 and B2 as the first two buildings under construction. |
| 2028-06-30 (projected) | 67 MW | 139,000 | Buildings 3-4 operational. Based on [Bravida](https://www.bravida.se/en/press/press-releases/2026/bravida-awarded-sek-650-million-installation-contract-in-borlange-by-ecodatacenter/) stating that installation work in another EcoDataCenter data center continues through Q1 2028, combined with permit documentation showing four data center buildings under construction by May 2026. |
Source: Epoch AI Frontier Data Centers.
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How clean is the power for EcoDataCenter 2?
The grid in Sweden emits about 36 g CO₂ per kWh (2025). Largest sources: hydro 40%, nuclear 27.4%, wind 22.8%.
Who operates EcoDataCenter 2?
Mistral AI. Reported users: Mistral AI.
Data centers near Borlänge
- EcoDataCenter 524 m · 97 MW
- DeepL Mercury 14.3 km · 0.8 MW
- Data center in Falun 14.4 km · 8 MW