Data Center Directory

EuroHPC Karolina

EuroHPC Karolina is an operational AI data center operated by EuroHPC JU in Ostrava, Czechia. Its power is about 0.5 MW. Epoch AI estimates about 182 H100-equivalent AI chips (NVIDIA A100).

Key facts

StatusOperational
OperatorEuroHPC JU
Facility power0.5 MW
Reported (Epoch AI or owner data)
AI compute182 H100-equivalents
AI chipsNVIDIA A100
Reported (Epoch AI or owner data)
Chip count576
Largest reported cluster at this site (Epoch AI).
GPU capacity if all AIabout 230 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
AddressStudentská 6231/1b, 708 00 Ostrava 8, Czechia
Coordinates49.83472, 18.15946

Power and grid

Nearest high-voltage substationMartinov, 110 kV, 2.1 km away (ČEZ Distribuce)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationLískovec, 220 kV, 18.3 km away
HV substations within 10 km12
Power plants within 50 km2.1 GW in 7 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity401 g CO₂ per kWh (Czechia, 2025)
Average of all power made in the area. Ember.
Grid power mixnuclear 42.3%, coal 35.2%, bioenergy 8%, solar 5.8%, gas 5.4%. Clean power: 59.2%
Industrial power priceEUR 0.154 per kWh (Czechia, 2026-S1)
Non-household users with 20 to 70 GWh per year, without VAT. Eurostat.

Climate and water

Average temperature8.7 °C
NASA POWER, average of 2001 to 2025.
Highest temperature36.6 °C (2001 to 2025)
Cooling degree days179 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.03 kWh per m² per day
Wind at 50 m6 m/s average
Water stress todayLow - Medium (10-20%) (Czechia)
Share of the local water supply that people already use. WRI Aqueduct 4.0, country level.
Water stress in 2050Medium - High (20-40%)
Business-as-usual scenario.

GPU clusters at this site

ClusterChipsCountPowerSince
EuroHPC KarolinaNVIDIA A1005760.5 MW2021-06-01

Source: Epoch AI GPU Clusters.

Satellite view

Questions

How much power does EuroHPC Karolina use?

Public data puts the facility power at about 0.5 MW. Reported (Epoch AI or owner data).

What chips does EuroHPC Karolina use?

Reported chips: NVIDIA A100.

How close is EuroHPC Karolina to the power grid?

The nearest high-voltage substation in OpenStreetMap is Martinov (110 kV), about 2.1 km away.

How clean is the power for EuroHPC Karolina?

The grid in Czechia emits about 401 g CO₂ per kWh (2025). Largest sources: nuclear 42.3%, coal 35.2%, bioenergy 8%.

Who operates EuroHPC Karolina?

EuroHPC JU.

Data centers near Ostrava

More EuroHPC JU data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.