Huawei Horinger

Huawei Horinger is an operational data center that is still expanding, operated by Huawei in Horinger, China. Its power is about 212 MW, growing to about 439 MW by 2028-02. Epoch AI estimates about 81,000 H100-equivalent AI chips (Ascend 910C, Ascend 910B).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorHuawei
Facility power212 MW
Reported (Epoch AI or owner data)
IT power170 MW
Planned power439 MW by 2028-02-17
Epoch AI timeline projection.
AI compute81,000 H100-equivalents → 141,000 planned
AI chipsAscend 910C, Ascend 910B
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 94,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 6.4 billion → 13.3 billion planned
Epoch AI estimate, 2025 USD.
AddressHuawei, Horinger, China
Coordinates40.29525, 111.90450 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2023-10-0800Land clearing begins simultaneously for all three zones (West, North, and South) after an official ceremony. The West and South zones later have the cooling capacity indicative of AI workloads, while the North Zone does not.
2025-02-2400In the West Zone, Building 1 is structurally complete. In the South Zone, Building 4 is structurally complete except for several cooling towers to be installed later. Buildings 2 (West Zone) and 5 (South Zone) have shells under construction.
2025-06-0800In the South Zone, paving and landscaping around Building 4 is mostly complete, while Building 5 still needs cooling and backup generators to be installed.
2025-06-1153 MW19,000In the West Zone, Building 1 is operational, based on its structural completion and colored motion artifacts on some of the cooling tower fans.
2026-03-0553 MW19,000Building 1 appears to have condensed water vapor above some cooling towers, suggesting they are still operating. Cooling towers have been added to Building 4, but we do not see any condensed water vapor, and there is still a crane over the building. So we don't think Building 4 is operational at full capacity yet.
2026-05-12109 MW41,000Building 4 is operational, based on its structural completion, the colored motion artifacts on some of the cooling tower fans, and cars parked out front (between the main building and the backup generator enclosure). Building 5 is almost structurally complete, but there is still some work to do in front of the backup generator enclosure.
2026-06-07109 MW41,000In the West Zone, Building 2 is structurally complete but still has some construction equipment around it.
2026-08-18212 MW81,000In the South Zone, Building 5 is operational, based on its structural completion, and the colored motion artifacts on the some of the cooling tower fans. Building 6 (South Zone) is under construction. In the West Zone, Building 3 has not begun construction.
2026-12-22 (projected)271 MW104,000In the West Zone, Building 2 is operational (estimate). A local government announcement said a "completion acceptance filing" was completed for Building 2 around September 23, 2026, "marking a critical step toward the project's entry into operation". We assume this corresponds to structural completion, since there was minimal construction activity by August 18th. We then allow 3 more months for a full fit-out of AI servers.
2028-02-17 (projected)439 MW141,000Building 6 (South Zone) is operational (estimate). This was the only new building under construction as of August 2026. We estimate the operational date based on an average of (1) previous buildings taking about 2 years on average from starting the building shell to becoming operational at ~full capacity, (2) a similar building at the Huawei Wuhu campus taking an estimated 550 days to become fully operational. Building 6 can reportedly support 100,000 AI accelerator cards and will deploy Huawei Ascend 950 chips. Based on the timing, we assume it has capacity for 100,000 Ascend 950DT chips (Ascend 950DT is ramping a few months later than 950PR). As with the other buildings, we multiply this capacity by the reported rack occupancy rate for the Horinger New Area (about 76%).

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-06-11Ascend 910C23,081Estimate
2025-06-11Ascend 910B7,694Estimate
2026-05-12Ascend 910C51,528Estimate
2026-08-18Ascend 910C104,716Estimate
2026-12-22Ascend 910C134,454Estimate
2028-02-17Ascend 950DT75,614Estimate

Satellite view

Questions

How much power does Huawei Horinger use?

Public data puts the facility power at about 212 MW, with about 439 MW planned by 2028. Reported (Epoch AI or owner data).

What chips does Huawei Horinger use?

Reported chips: Ascend 910C, Ascend 910B.

Who operates Huawei Horinger?

Huawei.