NCSA Petascale Computing Facility is an operational data center operated by NCSA in Champaign, United States. Our footprint estimate of its power is about 3.9 MW.

Key facts

StatusOperational
OperatorNCSA
Facility power3.9 MW (range 2 MW to 6.3 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 3,262 m² building outline x 1 floor(s) x 1.2 kW/m².
GPU capacity if all AIabout 1,700 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
AddressSouth Oak Street 1725, 61820, Champaign
Coordinates40.09526, -88.24203

Power and grid

UtilityEastern Illinois Elec Coop (cooperative)
Electric retail service territory (HIFLD, US government).
Balancing authorityMISO
Nearest gas pipelineTrunkline Gas Co, interstate pipeline, 7.7 km away
US Energy Information Administration pipeline map. Straight-line distance.
Grid carbon intensity247 g CO₂ per kWh (Illinois, 2025)
Average of all power made in the area. Ember.
Grid power mixnuclear 49.9%, gas 16.6%, coal 15.8%, wind 12.8%, solar 4.5%. Clean power: 67.3%
Industrial power priceUSD 0.113 per kWh (Illinois, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature11.4 °C
NASA POWER, average of 2001 to 2025.
Highest temperature42.1 °C (2001 to 2025)
Cooling degree days598 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.99 kWh per m² per day
Wind at 50 m6.8 m/s average
Water stress todayMedium - High (20-40%) (Illinois)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Medium - High (20-40%)
Business-as-usual scenario.

Satellite view

Questions

How much power does NCSA Petascale Computing Facility use?

We estimate the facility power at about 3.9 MW. Estimate from building footprint, low confidence.

How clean is the power for NCSA Petascale Computing Facility?

The grid in Illinois emits about 247 g CO₂ per kWh (2025). Largest sources: nuclear 49.9%, gas 16.6%, coal 15.8%.

Who operates NCSA Petascale Computing Facility?

NCSA.

Data centers near Champaign

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.