NOS Imopolis II
NOS Imopolis II is an operational data center operated by NOS in Carnaxide, Portugal. Our footprint estimate of its power is about 13 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | NOS |
| Facility power | 13 MW (range 6.4 MW to 20 MW) Estimate from building footprint, low confidence. Footprint estimate: about 10,650 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 5,600 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | NOS Imopolis I |
| Coordinates | 38.72512, -9.23054 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 220 kV, 1.7 km away (REN) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 9 |
| Power plants within 50 km | 1.9 GW in 44 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 128 g CO₂ per kWh (Portugal, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 29.7%, wind 26.8%, solar 17.3%, gas 16.5%, bioenergy 6.6%. Clean power: 80.9% |
| Industrial power price | EUR 0.090 per kWh (Portugal, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 16.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 43.7 °C (2001 to 2025) |
| Cooling degree days | 675 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.87 kWh per m² per day |
| Wind at 50 m | 6.1 m/s average |
| Water stress today | High (40-80%) (Portugal) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does NOS Imopolis II use?
We estimate the facility power at about 13 MW. Estimate from building footprint, low confidence.
How close is NOS Imopolis II to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (220 kV), about 1.7 km away.
How clean is the power for NOS Imopolis II?
The grid in Portugal emits about 128 g CO₂ per kWh (2025). Largest sources: hydro 29.7%, wind 26.8%, solar 17.3%.
Who operates NOS Imopolis II?
NOS.
Data centers near Carnaxide
- AtlasEdge DC Lisbon LIS001 130 m
- MEO LDV 1.2 km
- FCCN Lisbon - SE03 8.1 km
- Altice data center in Rio de Mouro 10.3 km
- Equinix LS1 - Lisbon 11.6 km · 4.6 MW
- dotsi - Lisbon DC01 11.8 km
- Seixal Colocation Site 15.2 km · 2.5 MW
- Data center in Alhandra 27.6 km · 12 MW
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.