Retelit S.p.A. Trento
Retelit S.p.A. Trento is an operational data center operated by Retelit in Trento, Italy. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Retelit |
| Networks | 3 networks PeeringDB. |
| Address | Viale Adriano Olivetti, 13 |
| Coordinates | 46.06163, 11.11534 |
| Website | retelit.it |
Power and grid
| Nearest high-voltage substation | Trento FS, 132 kV, 300 m away (Rete Ferroviaria Italiana) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Lavis, 220 kV, 7.6 km away |
| HV substations within 10 km | 5 |
| Power plants within 50 km | 1.3 GW in 19 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 285 g CO₂ per kWh (Italy, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 47.4%, solar 16.8%, hydro 15.7%, wind 8.1%, bioenergy 5.9%. Clean power: 48.7% |
| Industrial power price | EUR 0.173 per kWh (Italy, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 7.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 35.5 °C (2001 to 2025) |
| Cooling degree days | 64 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.57 kWh per m² per day |
| Wind at 50 m | 2 m/s average |
| Water stress today | Low - Medium (10-20%) (Trentino-Alto Adige) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Retelit S.p.A. Trento to the power grid?
The nearest high-voltage substation in OpenStreetMap is Trento FS (132 kV), about 300 m away.
How clean is the power for Retelit S.p.A. Trento?
The grid in Italy emits about 285 g CO₂ per kWh (2025). Largest sources: gas 47.4%, solar 16.8%, hydro 15.7%.
Who operates Retelit S.p.A. Trento?
Retelit.
Data centers near Trento
- Centrale TIM Trento Nord 2.6 km · 0.8 MW
- Intacture 26.5 km
- Sava di Valerio Francesca & C. SAS 48.2 km
- Bolzano - Infranet AG Datacenter 49.6 km
- Set 58.7 km · 0.5 MW
- 4ServiceSolutions 62.0 km
More Retelit data centers
- Retelit Avalon 3 Italy
- Retelit Avalon 2 Italy
- Retelit S.p.A. Roma Cornelia Italy
- Retelit S.p.A. Roma Perrier Italy