Rio AI City
Rio AI City is an operational data center in Barra da Tijuca, Brazil. Our footprint estimate of its power is about 69 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 69 MW (range 27 MW to 171 MW) Estimate from building footprint, low confidence. Footprint estimate: about 571,537 m² site outline x 0.12 kW per m² of land. |
| GPU capacity if all AI | about 29,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -22.96606, -43.37629 |
Power and grid
| Nearest high-voltage substation | Subestação Gardênia, 138 kV, 800 m away (Light) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Subestação Jacarepaguá, 345 kV, 6.6 km away |
| HV substations within 10 km | 10 |
| Power plants within 50 km | 3.4 GW in 6 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 23.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.1 °C (2001 to 2025) |
| Cooling degree days | 2,017 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.71 kWh per m² per day |
| Wind at 50 m | 4.1 m/s average |
| Water stress today | Low (<10%) (Rio de Janeiro) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Rio AI City use?
We estimate the facility power at about 69 MW. Estimate from building footprint, low confidence.
How close is Rio AI City to the power grid?
The nearest high-voltage substation in OpenStreetMap is Subestação Gardênia (138 kV), about 800 m away.
How clean is the power for Rio AI City?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Data centers near Barra da Tijuca
- NDX NET Servicos de Informatica 4.2 km
- Takoda RJ01 5.9 km
- Data center in Barra da Tijuca 7.1 km · 4.6 MW
- Tecto TGIG1 (ex Globenet CLS RJ) 7.6 km
- Nextel MSO RJO 10.2 km
- NEXUS RJ01 14.4 km
- Equinix RJ2 - Rio de Janeiro 15.0 km · 11 MW
- Moebius Datacenter 16.2 km
Sources
Correct this page or get the data