ScaleUp Datacenter BER03
ScaleUp Datacenter BER03 is an operational data center operated by ScaleUp Technologies in Berlin, Germany. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | ScaleUp Technologies |
| Networks | 8 networks, 1 internet exchanges PeeringDB. |
| Also known as | Penta Infra Berlin BER01 · Penta Infra Berlin BER02 |
| Address | Florastr. 133, 12623 Berlin |
| Coordinates | 52.51369, 13.61756 |
| Website | scaleuptech.com/de/rechenzentren/rechenzentrum-berlin-mahlsdorf |
Power and grid
| Nearest high-voltage substation | Umspannwerk Alt-Kaulsdorf, 110 kV, 2.4 km away (Vattenfall) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Umspannwerk Marzahn, 220 kV, 6.7 km away |
| HV substations within 10 km | 30 |
| Power plants within 50 km | 3.9 GW in 72 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 334 g CO₂ per kWh (Germany, 2025) Average of all power made in the area. Ember. |
| Grid power mix | wind 26.6%, coal 21%, solar 18%, gas 16.8%, bioenergy 10.1%. Clean power: 58.5% |
| Industrial power price | EUR 0.146 per kWh (Germany, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 9.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.2 °C (2001 to 2025) |
| Cooling degree days | 209 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.83 kWh per m² per day |
| Wind at 50 m | 6.6 m/s average |
| Water stress today | Medium - High (20-40%) (Germany) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is ScaleUp Datacenter BER03 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Umspannwerk Alt-Kaulsdorf (110 kV), about 2.4 km away.
How clean is the power for ScaleUp Datacenter BER03?
The grid in Germany emits about 334 g CO₂ per kWh (2025). Largest sources: wind 26.6%, coal 21%, solar 18%.
Who operates ScaleUp Datacenter BER03?
ScaleUp Technologies.
Data centers near Berlin
- Datacenter Berlin Mahlsdorf (RZB) - PŸUR Business 73 m · 4.4 MW
- Umspannwerk Berlin 12.9 km
- Versatel Berlin 14.4 km
- NorthC Berlin 14.5 km · 4.4 MW
- Aleph Alpha alpha ONE 16.1 km · 0.4 MW
- 3U Rechenzentrum Berlin 16.8 km
- Pixelpark GmbH Colo II Berlin 16.8 km
- Speedbone Berlin 17.6 km · 0.9 MW
Sources
Correct this page or get the data