VNET Bayin Ulanqab is an operational data center that is still expanding, operated by ByteDance in Ulanqab, China. Its power is about 252 MW, growing to about 798 MW by 2027-09. Epoch AI estimates about 123,000 H100-equivalent AI chips (Ascend 910C).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorByteDance
UsersByteDance (speculative)
Project10 GW Hyperscale 2.0
Facility power252 MW
Reported (Epoch AI or owner data)
IT power221 MW
Planned power798 MW by 2027-09-01
Epoch AI timeline projection.
AI compute123,000 H100-equivalents → 388,000 planned
AI chipsAscend 910C
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 120,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 8.4 billion → 26.5 billion planned
Epoch AI estimate, 2025 USD.
AddressBayin, Ulanqab, China
Coordinates41.62415, 112.63250

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-03-2500Land clearing begins late March, as can be seen in satellite images (eastern part: buildings 1 & 2). VNET officially [announces](https://web.archive.org/web/20250620154431/https://www.vnet.com/portal/article/index/cid/14/id/876.html) its signing ceremony with the Ulanqab municipal government and Shandong Hi-Speed Holdings.
2025-02-0500Satellite imagery shows five buildings (1, 2, 3, 4, 5) under construction. Chillers are in place, but no roof is complete for any building.
2025-07-0143 MW21,000Building 1 is operational, based on a 3-month fit-out period after structural completion in April, as can be seen from satellite imagery.
2025-08-0143 MW21,000Satellite imagery shows that in total nine buildings have started construction, with building 1 being the only one operational. Buildings 2 and 5 are structurally complete, and the final roofs for buildings 3 and 4 have begun.
2025-11-01194 MW94,000Buildings 2 and 5 are operational, based on a 3-month fit-out period after structural completion in August, as can be seen from satellite imagery. Land clearing for the northern part of campus (buildings 10 and 11) has started.
2025-12-01252 MW123,000Building 4 is operational, similarly based on a 3-month fit-out period after structural completion in September, as seen from satellite imagery.
2026-03-05252 MW123,000Satellite imagery shows four operational buildings (1, 2, 4, 5), and the western part of campus (6, 7, 8, 9) has made significant construction progress. The foundation for the northern part of campus (10, 11) has started.
2026-05-06252 MW123,000Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining. Previous building completion timelines would imply this building will be operational by the end of 2026.
2027-09-01 (projected)798 MW388,000Estimated: the nine-building section of the campus is projected to be fully operational by late 2027 or early 2028. VNET's eastern cluster (buildings 1-5) took roughly a year each from clearing to operational based on satellite imagery. The western cluster (buildings 6-9) was cleared in late 2024 but as of mid-2026 is not yet structurally complete, putting each on track for ~2 years from clearing to operational. Buildings 10 and 11 are projected to be completed sometime later. Comparable data centers in Ulanqab are expected to take at least 6 months per phase ([China Unicom](https://archive.ph/bJDHl)).

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-07-01Ascend 910C27,568Estimate
2025-11-01Ascend 910C124,512Estimate
2025-12-01Ascend 910C161,296Estimate

Satellite view

Questions

How much power does VNET Bayin Ulanqab use?

Public data puts the facility power at about 252 MW, with about 798 MW planned by 2027. Reported (Epoch AI or owner data).

What chips does VNET Bayin Ulanqab use?

Reported chips: Ascend 910C.

Who operates VNET Bayin Ulanqab?

ByteDance. Reported users: ByteDance.

Data centers near Ulanqab

More ByteDance data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.