VNET Bayin Ulanqab
VNET Bayin Ulanqab is an operational data center that is still expanding, operated by ByteDance in Ulanqab, China. Its power is about 252 MW, growing to about 798 MW by 2027-09. Epoch AI estimates about 123,000 H100-equivalent AI chips (Ascend 910C).
Power demand is growing at this site
Key facts
| Status | Operational, expanding |
|---|---|
| Operator | ByteDance |
| Users | ByteDance (speculative) |
| Project | 10 GW Hyperscale 2.0 |
| Facility power | 252 MW Reported (Epoch AI or owner data) |
| IT power | 221 MW |
| Planned power | 798 MW by 2027-09-01 Epoch AI timeline projection. |
| AI compute | 123,000 H100-equivalents → 388,000 planned |
| AI chips | Ascend 910C Reported (Epoch AI or owner data) |
| GPU capacity if all AI | about 120,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Capital cost | USD 8.4 billion → 26.5 billion planned Epoch AI estimate, 2025 USD. |
| Address | Bayin, Ulanqab, China |
| Coordinates | 41.62415, 112.63250 |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2024-03-25 | 0 | 0 | Land clearing begins late March, as can be seen in satellite images (eastern part: buildings 1 & 2). VNET officially [announces](https://web.archive.org/web/20250620154431/https://www.vnet.com/portal/article/index/cid/14/id/876.html) its signing ceremony with the Ulanqab municipal government and Shandong Hi-Speed Holdings. |
| 2025-02-05 | 0 | 0 | Satellite imagery shows five buildings (1, 2, 3, 4, 5) under construction. Chillers are in place, but no roof is complete for any building. |
| 2025-07-01 | 43 MW | 21,000 | Building 1 is operational, based on a 3-month fit-out period after structural completion in April, as can be seen from satellite imagery. |
| 2025-08-01 | 43 MW | 21,000 | Satellite imagery shows that in total nine buildings have started construction, with building 1 being the only one operational. Buildings 2 and 5 are structurally complete, and the final roofs for buildings 3 and 4 have begun. |
| 2025-11-01 | 194 MW | 94,000 | Buildings 2 and 5 are operational, based on a 3-month fit-out period after structural completion in August, as can be seen from satellite imagery. Land clearing for the northern part of campus (buildings 10 and 11) has started. |
| 2025-12-01 | 252 MW | 123,000 | Building 4 is operational, similarly based on a 3-month fit-out period after structural completion in September, as seen from satellite imagery. |
| 2026-03-05 | 252 MW | 123,000 | Satellite imagery shows four operational buildings (1, 2, 4, 5), and the western part of campus (6, 7, 8, 9) has made significant construction progress. The foundation for the northern part of campus (10, 11) has started. |
| 2026-05-06 | 252 MW | 123,000 | Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining. Previous building completion timelines would imply this building will be operational by the end of 2026. |
| 2027-09-01 (projected) | 798 MW | 388,000 | Estimated: the nine-building section of the campus is projected to be fully operational by late 2027 or early 2028. VNET's eastern cluster (buildings 1-5) took roughly a year each from clearing to operational based on satellite imagery. The western cluster (buildings 6-9) was cleared in late 2024 but as of mid-2026 is not yet structurally complete, putting each on track for ~2 years from clearing to operational. Buildings 10 and 11 are projected to be completed sometime later. Comparable data centers in Ulanqab are expected to take at least 6 months per phase ([China Unicom](https://archive.ph/bJDHl)). |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2025-07-01 | Ascend 910C | 27,568 | Estimate |
| 2025-11-01 | Ascend 910C | 124,512 | Estimate |
| 2025-12-01 | Ascend 910C | 161,296 | Estimate |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does VNET Bayin Ulanqab use?
Public data puts the facility power at about 252 MW, with about 798 MW planned by 2027. Reported (Epoch AI or owner data).
What chips does VNET Bayin Ulanqab use?
Reported chips: Ascend 910C.
Who operates VNET Bayin Ulanqab?
ByteDance. Reported users: ByteDance.
Data centers near Ulanqab
- Data center in Jining 77.8 km · 36 MW
- Data center in Jining 77.9 km · 15 MW
More ByteDance data centers
- Bridge Data Centres MY06 Malaysia
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.