Connect Cedar Valley
Connect Cedar Valley is an operational data center operated by Connect Des Moines in Cedar Falls, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Connect Des Moines |
| Networks | 2 networks PeeringDB. |
| Also known as | Cologix DSM2 |
| Address | 1205 Technology Pkwy |
| Coordinates | 42.47417, -92.45879 |
| Website | connectdsm.com |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 161 kV, 700 m away (Cedar Falls Utilities) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 345 kV, 15.8 km away |
| HV substations within 10 km | 8 |
| Utility | Cedar Falls Utilities (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | MISO |
| Nearest gas pipeline | Northern Natural Gas Co, interstate pipeline, 9.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 411 MW in 8 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 313 g CO₂ per kWh (Iowa, 2025) Average of all power made in the area. Ember. |
| Grid power mix | wind 58.5%, coal 25.6%, gas 11.6%, solar 2.5%, hydro 1.4%. Clean power: 62.8% |
| Industrial power price | USD 0.093 per kWh (Iowa, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 8.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.8 °C (2001 to 2025) |
| Cooling degree days | 424 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.02 kWh per m² per day |
| Wind at 50 m | 6.9 m/s average |
| Water stress today | Low - Medium (10-20%) (Iowa) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Connect Cedar Valley to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (161 kV), about 700 m away. The local utility is Cedar Falls Utilities, in the MISO balancing area.
How clean is the power for Connect Cedar Valley?
The grid in Iowa emits about 313 g CO₂ per kWh (2025). Largest sources: wind 58.5%, coal 25.6%, gas 11.6%.
Who operates Connect Cedar Valley?
Connect Des Moines.
Data centers near Cedar Falls
- SFN IA-Waterloo 10.6 km
- Heartland Technology Data Center 33.2 km
- SFN IA-Urbana 53.4 km
- Enseva Cedar Rapids 79.2 km
- QTS Cedar Rapids 86.0 km
- Google Cedar Rapids 86.7 km
- ark data centers - Cedar Rapids ,IA 88.0 km
- DartPoints North Liberty, IA 106.8 km
More Connect Des Moines data centers
- Connect Des Moines United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.