CX2 / MY01 Cyberjaya Malaysia
CX2 / MY01 Cyberjaya Malaysia is an operational data center operated by Bridge Data Centres in Cyberjaya, Malaysia. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Bridge Data Centres |
| Networks | 28 networks, 3 internet exchanges PeeringDB. |
| Also known as | PLTPRO Data Centre · TM ONE CBJ6, Cyberjaya |
| Address | MY02, 7118 Jalan Impact |
| Coordinates | 2.91713, 101.66188 |
| Website | bridgedatacentres.com |
Power and grid
| Nearest high-voltage substation | PMU 132/33kV Cyberjaya Central GIS (CBJC), 132 kV, 1.6 km away (Tenaga Nasional) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | PMU GIS Cybersouth 4, 275 kV, 1.9 km away |
| HV substations within 10 km | 9 |
| Power plants within 50 km | 10 GW in 12 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 601 g CO₂ per kWh (Malaysia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 44.5%, gas 33.2%, hydro 16.3%, solar 3.9%, oil and other fossil 1.3%. Clean power: 21% |
Climate and water
| Average temperature | 27.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 33.2 °C (2001 to 2025) |
| Cooling degree days | 3,495 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.8 kWh per m² per day |
| Wind at 50 m | 3.1 m/s average |
| Water stress today | Low (<10%) (Selangor) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is CX2 / MY01 Cyberjaya Malaysia to the power grid?
The nearest high-voltage substation in OpenStreetMap is PMU 132/33kV Cyberjaya Central GIS (CBJC) (132 kV), about 1.6 km away.
How clean is the power for CX2 / MY01 Cyberjaya Malaysia?
The grid in Malaysia emits about 601 g CO₂ per kWh (2025). Largest sources: coal 44.5%, gas 33.2%, hydro 16.3%.
Who operates CX2 / MY01 Cyberjaya Malaysia?
Bridge Data Centres.
Data centers near Cyberjaya
- CSF CX1 / TelcoHub1 Kuala Lumpur 817 m
- CX5 / MY02 Cyberjaya Malaysia 1.4 km · 4.5 MW
- TM ONE CBJ1, Cyberjaya 1.6 km
- Data Center KUL75 1.7 km · 14 MW
- Keppel Data Centres | Basis Bay Data Centre 1.7 km
- STTGDC KUL1 1.7 km · 0.7 MW
- Bridge Data Centres - MY02-C2 1.8 km · 13 MW
- TMONE Klang Valley Data Center 1.8 km · 5.4 MW
More Bridge Data Centres data centers
- CX5 / MY02 Cyberjaya Malaysia Malaysia
- BBY01 India
- BKK01 Thailand
- MY03 Malaysia
- MY06 Malaysia
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.