DayOne Kempas

DayOne Kempas is an operational AI data center in Johor, Malaysia. Its power is about 590 MW. Epoch AI estimates about 481,000 H100-equivalent AI chips (B300).

Key facts

StatusOperational
Facility power590 MW
Reported (Epoch AI or owner data)
IT power422 MW
AI compute481,000 H100-equivalents
AI chipsB300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 230,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 16.0 billion
Epoch AI estimate, 2025 USD.
AddressHP79+MP, 81300 Johor Bahru, Johor, Malaysia
Coordinates1.52877, 103.70505 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2023-11-1100Land clearing begins.
2025-09-1500In this [video](https://www.youtube.com/watch?v=HODHjDbFt10) at 6:28, some fans can be seen in motion for Building 3. However, we think it's unlikely that any buildings are at fully operational capacity yet. Buildings 1-4 are roofed. Building 5-6 shells are underway.
2026-01-22112 MW91,000Buildings 3 and 4 are operational. This is based on construction looking complete, and DayOne [reporting](https://archive.is/8CFXN) 390 MW "in service" across both Nusajaya and Kempas campuses as of Jan 30. Subtracting our [Nusajaya estimates](https://epoch.ai/data/ai-data-centers/directory/dayone-nusajaya) (69.5 MW excluded in Phase 1 + 240.3 MW AI) implies ~80 MW in service at KTP, consistent with roughly 2 buildings per our ~49.6 MW per-building estimate, but not at full capacity. Buildings 1 and 2 look complete with rooftop cooling equipment installed (32 units each, in 2 strips of 16). The units are almost all single-fan cells; Building 2 has one strip of 16 single-fan cells and one darker bank of 16 long multi-fan air-cooled (slat) units - this suggests an cell-to-air-cooled power equivalence that informs our power estimates. The smaller Building 9 (west of Building 1, half fit-out: 16 cells) also has its cooling installed. Building 5 has rooftop equipment partially installed; Building 6 is roofed; Buildings 7-8 shells are still underway.
2026-06-01313 MW254,000Buildings 1-4 and the smaller Building 9 assumed fully operational: cooling equipment was installed by Jan 2026 (Building 9 on the same timeline as Building 1) and the implied KTP in-service figure (~80 MW) shows them ramping in early 2026, so we allow ~3 more months to reach full capacity. Rooftop equipment texture is visible campus-wide.
2026-08-10313 MW254,000Buildings 5-6 look complete and parking lot activity suggests they are nearly operational. Building 7-8 nearing completion with some construction equipment still in their vicinity.
2026-09-01451 MW368,000Buildings 5-6 assumed operational. These buildings were roofed between Sep and Dec 2025 and equipment fit-out was underway in Jan 2026; applying the default roof-to-operational delay plus ramp time approximates their operability to this date.
2026-10-01590 MW481,000Buildings 7-8 assumed operational. These buildings were roofed by March 2026 and by August 2026 their cooling and backup power equipment looked complete. With an additional two months of commissioning after August we approximate their operability to this date.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-01-22B30036,179Estimate
2026-06-01B300100,714Estimate
2026-09-01B300145,475Estimate
2026-10-01B300190,237Estimate

Satellite view

Questions

How much power does DayOne Kempas use?

Public data puts the facility power at about 590 MW. Reported (Epoch AI or owner data).

What chips does DayOne Kempas use?

Reported chips: B300.

Data centers near Johor

Sources