Dell Rattler
Dell Rattler is an operational AI data center operated by Dell Technologies in Austin, United States. Its power is about 0.2 MW. Epoch AI estimates about 61 H100-equivalent AI chips (NVIDIA A100).
Key facts
| Status | Operational |
|---|---|
| Operator | Dell Technologies |
| Facility power | 0.2 MW Reported (Epoch AI or owner data) |
| AI compute | 61 H100-equivalents |
| AI chips | NVIDIA A100 Reported (Epoch AI or owner data) |
| Chip count | 192 Largest reported cluster at this site (Epoch AI). |
| GPU capacity if all AI | about 70 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Austin, Texas |
| Coordinates | 30.26807, -97.74281 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 138 kV, 800 m away (Austin Energy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 345 kV, 12.9 km away |
| HV substations within 10 km | 24 |
| Utility | Austin Energy (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | ERCO |
| Nearest gas pipeline | Houston Pipeline Co, intrastate pipeline, 2.7 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 4.1 GW in 18 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 379 g CO₂ per kWh (Texas, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8% |
| Industrial power price | USD 0.072 per kWh (Texas, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 20.2 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 44.6 °C (2001 to 2025) |
| Cooling degree days | 1,779 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.81 kWh per m² per day |
| Wind at 50 m | 6.2 m/s average |
| Water stress today | High (40-80%) (Texas) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
GPU clusters at this site
| Cluster | Chips | Count | Power | Since |
|---|---|---|---|---|
| Dell Rattler | NVIDIA A100 | 192 | 0.2 MW | 2021-11-01 |
Source: Epoch AI GPU Clusters.
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Dell Rattler use?
Public data puts the facility power at about 0.2 MW. Reported (Epoch AI or owner data).
What chips does Dell Rattler use?
Reported chips: NVIDIA A100.
How close is Dell Rattler to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (138 kV), about 800 m away. The local utility is Austin Energy, in the ERCO balancing area.
How clean is the power for Dell Rattler?
The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.
Who operates Dell Rattler?
Dell Technologies.
Data centers near Austin
- 1011 San Jacinto 571 m
- BESTNAP 608 m
- Lumen Austin 3 2.0 km · 0.8 MW
- Alpheus Austin (1905 E. 6th Street) 2.1 km · 4.9 MW
- LightEdge Austin 1 (AUS1) 6.6 km · 5.3 MW
- Data Foundry Austin 1 7.5 km · 9.1 MW
- Digital Realty AUS11 - Austin 7.7 km · 19 MW
- Cogent Austin 7.8 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.