Experian is an operational data center in Nottingham, United Kingdom. Our footprint estimate of its power is about 13 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 13 MW (range 6.4 MW to 20 MW) Estimate from building footprint, low confidence. Footprint estimate: about 10,659 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 5,600 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Mere Way, NG80 1DP, Nottingham |
| Coordinates | 52.87962, -1.14496 |
Power and grid
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 9.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 31.5 °C (2001 to 2025) |
| Cooling degree days | 14 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.73 kWh per m² per day |
| Wind at 50 m | 7.2 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Experian use?
We estimate the facility power at about 13 MW. Estimate from building footprint, low confidence.
How clean is the power for Experian?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Data centers near Nottingham
- CWCS DCN3 6.4 km
- The Portal Data Centre (Flexiscale DC 1) 7.2 km
- iomart DC3 Nottingham 7.9 km
- nLighten Nottingham EMA1 14.9 km
- nLighten Nottingham 14.9 km · 8.7 MW
- Grid Hosting Limited 22.4 km
- Digital Space DC - Newark 32.4 km
- Santander data center in Enderby 33.2 km · 8.8 MW
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.