maincubes FRA01 is an operational data center operated by maincubes one in Offenbach, Germany. Our footprint estimate of its power is about 2 MW.

Key facts

StatusOperational
Operatormaincubes one
Facility power2 MW (range 0.8 MW to 5.1 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 16,928 m² site outline x 0.12 kW per m² of land.
GPU capacity if all AIabout 850 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Networks39 networks, 6 internet exchanges
PeeringDB.
Also known asKeppel Data Centres | maincubes Data Centre
AddressGoethering 29
Coordinates50.10930, 8.74229
Websitemaincubes.com

Power and grid

Nearest high-voltage substation110 KV Schaltanlage, 110 kV, 200 m away (Energieversorgung Offenbach)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationUmspannwerk Frankfurt Nord, 220 kV, 5.6 km away
HV substations within 10 km31
Power plants within 50 km3.0 GW in 44 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity334 g CO₂ per kWh (Germany, 2025)
Average of all power made in the area. Ember.
Grid power mixwind 26.6%, coal 21%, solar 18%, gas 16.8%, bioenergy 10.1%. Clean power: 58.5%
Industrial power priceEUR 0.146 per kWh (Germany, 2026-S1)
Non-household users with 20 to 70 GWh per year, without VAT. Eurostat.

Climate and water

Average temperature10.3 °C
NASA POWER, average of 2001 to 2025.
Highest temperature39.8 °C (2001 to 2025)
Cooling degree days233 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy2.98 kWh per m² per day
Wind at 50 m5.7 m/s average
Water stress todayMedium - High (20-40%) (Germany)
Share of the local water supply that people already use. WRI Aqueduct 4.0, country level.
Water stress in 2050Medium - High (20-40%)
Business-as-usual scenario.

Satellite view

Questions

How much power does maincubes FRA01 use?

We estimate the facility power at about 2 MW. Estimate from building footprint, low confidence.

How close is maincubes FRA01 to the power grid?

The nearest high-voltage substation in OpenStreetMap is 110 KV Schaltanlage (110 kV), about 200 m away.

How clean is the power for maincubes FRA01?

The grid in Germany emits about 334 g CO₂ per kWh (2025). Largest sources: wind 26.6%, coal 21%, solar 18%.

Who operates maincubes FRA01?

maincubes one.

Data centers near Offenbach

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.