Data Center Directory

Meta Jeffersonville

Meta Jeffersonville is an operational AI data center operated by Meta in Jeffersonville, United States. Its power is about 241 MW. Epoch AI estimates about 203,000 H100-equivalent AI chips (B300).

Key facts

StatusOperational
OperatorMeta
UsersMeta
Facility power241 MW
Reported (Epoch AI or owner data)
IT power178 MW
AI compute203,000 H100-equivalents
AI chipsB300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 99,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 6.7 billion
Epoch AI estimate, 2025 USD.
Address500 8th St, Jeffersonville, IN 47130, USA
Coordinates38.27913, -85.73901

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-02-0100Land clearing begins.
2026-03-0600Building 1 and 2 shell and cooling look complete, but there's still construction activity. We give it another 3 months to operational.
2026-06-04241 MW203,000Building 1 and 2 are operational.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-06-04B30080,486Estimate

Satellite view

Questions

How much power does Meta Jeffersonville use?

Public data puts the facility power at about 241 MW. Reported (Epoch AI or owner data).

What chips does Meta Jeffersonville use?

Reported chips: B300.

Who operates Meta Jeffersonville?

Meta. Reported users: Meta.

Data centers near Jeffersonville

More Meta data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.