Meta Kuna
Meta Kuna is an operational AI data center operated by Meta in Kuna, United States. Its power is about 198 MW. Epoch AI estimates about 173,000 H100-equivalent AI chips (B300).
Key facts
| Status | Operational |
|---|---|
| Operator | Meta |
| Users | Meta |
| Facility power | 198 MW Reported (Epoch AI or owner data) |
| IT power | 152 MW |
| AI compute | 173,000 H100-equivalents |
| AI chips | B300 Reported (Epoch AI or owner data) |
| GPU capacity if all AI | about 84,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Capital cost | USD 5.8 billion Epoch AI estimate, 2025 USD. |
| Water use | 0.07 million gallons per day |
| Energy partners | Idaho Power Company |
| Address | 601 Kuna Mora Rd, Kuna ID 83634 |
| Coordinates | 43.45921, -116.42111 |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2022-07-01 | 0 | 0 | Land clearing begins. |
| 2026-03-15 | 0 | 0 | Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Construction has started on 2 smaller buildings to the north. Meta announced the arrival of the first server rack the following week. |
| 2026-06-01 | 198 MW | 173,000 | Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings. |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2026-06-01 | B300 | 68,571 | Estimate |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Meta Kuna use?
Public data puts the facility power at about 198 MW. Reported (Epoch AI or owner data).
What chips does Meta Kuna use?
Reported chips: B300.
Who operates Meta Kuna?
Meta. Reported users: Meta.
Data centers near Kuna
- Data center in Kuna 12.0 km · 33 MW
- Data center in Kuna 12.3 km · 27 MW
- Meta Kuna Data Center 12.7 km · 300 MW
More Meta data centers
- Meta Hyperion United States
- QTS Cedar Rapids United States
- Meta Prometheus United States
- Meta Bowling Green United States
- Meta Montgomery United States
- QTS Eagle Mountain United States
- Meta Huntsville Data Center United States
- Altoona Meta Data Center United States
Sources
- Epoch AI, Frontier Data Centers
- Official Pamphlet from Meta
- Application for Power Purchase Agreement, Pleasant Valley Solar 1
- Application for Power Purchase Agreement, Pleasant Valley Solar 2
- Approval to move start date of Solar 2 to May 31, 2026
- staff comments
- Notice of Application for 3rd PPA (Blacks Creek Energy Center)
- Idaho Statesman: Peak construction reached in March 2025
- Idaho Statesman: Expected water usage reported in 2022
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.