Mobistar Nossegem fka Versatel Nossegem
Mobistar Nossegem fka Versatel Nossegem is an operational data center operated by Mobistar Enterprise Services in Nossegem, Belgium. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Mobistar Enterprise Services |
| Networks | 4 networks PeeringDB. |
| Address | Leuvensesteenweg 641 |
| Coordinates | 50.87757, 4.50364 |
| Website | corporate.mobistar.be |
Power and grid
| Nearest high-voltage substation | Woluwe-Saint-Lambert - Sint-Lambrechts-Woluwe, 150 kV, 4.3 km away (Elia) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | 380 kV Station Verbrande Brug, 380 kV, 9.3 km away |
| HV substations within 10 km | 8 |
| Power plants within 50 km | 2.0 GW in 18 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 151 g CO₂ per kWh (Belgium, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 33.5%, gas 20.8%, wind 18.6%, solar 14.5%, oil and other fossil 7.1%. Clean power: 72.1% |
| Industrial power price | EUR 0.133 per kWh (Belgium, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.6 °C (2001 to 2025) |
| Cooling degree days | 87 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.03 kWh per m² per day |
| Wind at 50 m | 6.7 m/s average |
| Water stress today | Extremely High (>80%) (Belgium) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Mobistar Nossegem fka Versatel Nossegem to the power grid?
The nearest high-voltage substation in OpenStreetMap is Woluwe-Saint-Lambert - Sint-Lambrechts-Woluwe (150 kV), about 4.3 km away.
How clean is the power for Mobistar Nossegem fka Versatel Nossegem?
The grid in Belgium emits about 151 g CO₂ per kWh (2025). Largest sources: nuclear 33.5%, gas 20.8%, wind 18.6%.
Who operates Mobistar Nossegem fka Versatel Nossegem?
Mobistar Enterprise Services.
Data centers near Nossegem
- Unix-Solutions DC Zaventem 386 m · 0.8 MW
- Digital Realty BRU3 - Brussels 433 m · 4.9 MW
- AtlasEdge DC Brussels BRU001 617 m · 8.5 MW
- EXA Edge DC Zaventem 1.1 km
- Digital Realty BRU1 - Brussels 2.0 km · 9.6 MW
- brusselsdc 3.5 km · 1.3 MW
- LCL Brussels (Diegem) 3.6 km
- MCI/Verizon Brussels (Diegem) E 3.8 km
Sources
Correct this page or get the data