Paratus Vanguard is an operational data center operated by Paratus in Lusaka, Zambia. No power figure is public for this site yet.

Key facts

StatusOperational
OperatorParatus
Networks1 networks
PeeringDB.
Address34 Bwinjimfumu Rd
Coordinates-15.40768, 28.29361
Websiteparatus.africa/zm

Power and grid

Nearest high-voltage substationCoventry, 132 kV, 2.3 km away (ZESCO)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationZesco Water Works, 330 kV, 5.5 km away
HV substations within 10 km4
Power plants within 50 km168 MW in 4 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity125 g CO₂ per kWh (Zambia, 2024)
Average of all power made in the area. Ember.
Grid power mixhydro 85.7%, coal 10.7%, oil and other fossil 1.7%, solar 1.5%. Clean power: 87.6%

Climate and water

Average temperature22.2 °C
NASA POWER, average of 2001 to 2025.
Highest temperature41.5 °C (2001 to 2025)
Cooling degree days1,653 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy5.73 kWh per m² per day
Wind at 50 m5.5 m/s average
Water stress todayLow (<10%) (Zambia)
Share of the local water supply that people already use. WRI Aqueduct 4.0, country level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How close is Paratus Vanguard to the power grid?

The nearest high-voltage substation in OpenStreetMap is Coventry (132 kV), about 2.3 km away.

How clean is the power for Paratus Vanguard?

The grid in Zambia emits about 125 g CO₂ per kWh (2024). Largest sources: hydro 85.7%, coal 10.7%, oil and other fossil 1.7%.

Who operates Paratus Vanguard?

Paratus.

More Paratus data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.