PIX Sempre (Brasil TecPar)
PIX Sempre (Brasil TecPar) is an operational data center operated by Brasil TecPar in Belo Horizonte, Brazil. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Brasil TecPar |
| Networks | 3 networks, 1 internet exchanges PeeringDB. |
| Address | Avenida Marcelo Diniz Xavier, 649, Califórnia |
| Coordinates | -19.92907, -44.02449 |
| Website | ix.br/adesao/mg |
Power and grid
| Nearest high-voltage substation | Subestação Atalaia, 138 kV, 1.4 km away (Cemig) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Subestação Barreiro, 345 kV, 8.7 km away |
| HV substations within 10 km | 14 |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 20.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.7 °C (2001 to 2025) |
| Cooling degree days | 1,000 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.02 kWh per m² per day |
| Wind at 50 m | 4.9 m/s average |
| Water stress today | Low (<10%) (Minas Gerais) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is PIX Sempre (Brasil TecPar) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Subestação Atalaia (138 kV), about 1.4 km away.
How clean is the power for PIX Sempre (Brasil TecPar)?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Who operates PIX Sempre (Brasil TecPar)?
Brasil TecPar.
Data centers near Belo Horizonte
- PIX Century Telecom - Belo Horizonte 4.0 km
- Data Center (Ministério Público de Minas Gerais) 4.8 km · 0.9 MW
- Eletronet - Belo Horizonte 8.4 km
- PoP-MG 9.1 km
- PIX Prodabel 9.2 km
- G8 Teleporto Serra do Curral Belo Horizonte 9.6 km
- MASTER DA WEB 10.6 km
- PIX Vogel Telecom BH 10.6 km
More Brasil TecPar data centers
Sources
Correct this page or get the data