Segro Croydon (Morgan Stanley)
Segro Croydon (Morgan Stanley) is an operational data center operated by Morgan Stanley in Croydon, United Kingdom. Our footprint estimate of its power is about 24 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Morgan Stanley |
| Facility power | 24 MW (range 12 MW to 39 MW) Estimate from building footprint, low confidence. Footprint estimate: about 20,350 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 10,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 51.38398, -0.13590 |
| Website | segro.com/countries-repository/united-kingdom/segro-park-croydon-beddington-lane |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 132 kV, 100 m away (UK Power Networks) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Beddington Substation, 400 kV, 1.3 km away |
| HV substations within 10 km | 16 |
| Power plants within 50 km | 3.1 GW in 98 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 10.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34 °C (2001 to 2025) |
| Cooling degree days | 46 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.97 kWh per m² per day |
| Wind at 50 m | 7.2 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Segro Croydon (Morgan Stanley) use?
We estimate the facility power at about 24 MW. Estimate from building footprint, low confidence.
How close is Segro Croydon (Morgan Stanley) to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (132 kV), about 100 m away.
How clean is the power for Segro Croydon (Morgan Stanley)?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Who operates Segro Croydon (Morgan Stanley)?
Morgan Stanley.
Data centers near Croydon
- Croydon 129 m · 11 MW
- Pulsant Croydon LN-1 3.6 km · 4.5 MW
- WRN Broadcast 10.9 km · 1.1 MW
- Digital Realty LHR13 10.9 km · 9.2 MW
- Citibank Riverdale Data Centre 12.1 km · 17 MW
- Netwise London Central (NLC) 13.4 km
- Digital Realty London LHR13 14.4 km
- DataGrid Network London 14.5 km
More Morgan Stanley data centers
- Morgan Stanley Data Centre United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.