Sentech data center in Durbanville
Sentech data center in Durbanville is an operational data center operated by Sentech in Durbanville, South Africa. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Sentech |
| Coordinates | -33.87522, 18.59552 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 132 kV, 2.8 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Acacia Park Substation, 400 kV, 5.6 km away |
| HV substations within 10 km | 15 |
| Power plants within 50 km | 3.7 GW in 12 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 699 g CO₂ per kWh (South Africa, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 81.3%, solar 8%, wind 4.7%, nuclear 4.2%, oil and other fossil 0.8%. Clean power: 17.9% |
Climate and water
| Average temperature | 16.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.7 °C (2001 to 2025) |
| Cooling degree days | 449 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.56 kWh per m² per day |
| Wind at 50 m | 6.3 m/s average |
| Water stress today | Extremely High (>80%) (Western Cape) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Sentech data center in Durbanville to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (132 kV), about 2.8 km away.
How clean is the power for Sentech data center in Durbanville?
The grid in South Africa emits about 699 g CO₂ per kWh (2025). Largest sources: coal 81.3%, solar 8%, wind 4.7%.
Who operates Sentech data center in Durbanville?
Sentech.
Data centers near Durbanville
- Amazon AWS CPT - Atlantic 8.0 km · 7.4 MW
- Teraco CT2 Cape Town, South Africa 8.5 km · 18 MW
- Data center in Kuils River 8.6 km · 25 MW
- OADC CPT1 - Cape Town 14.4 km
- OADC Rondebosch 14.8 km · 4.8 MW
- Teraco CT1 Cape Town, South Africa 16.1 km
- OADC CPT3 - Cape Town 16.9 km
- Amazon Web Services 20.5 km · 12 MW
Sources
Correct this page or get the data