Tecto TFOR3 (ex Mega Lobster)
Tecto TFOR3 (ex Mega Lobster) is an operational data center operated by Tecto Data Centers in Fortaleza, Brazil. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Tecto Data Centers |
| Networks | 2 networks PeeringDB. |
| Address | Av. Dioguinho & R. Francisco Montenegro |
| Coordinates | -3.75561, -38.44768 |
| Website | tecto.com |
Power and grid
| Nearest high-voltage substation | Subestação Delmiro Gouveia, 230 kV, 8.3 km away (Companhia Hidro Elétrica do São Francisco) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 1 |
| Power plants within 50 km | 572 MW in 3 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 26.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 36.9 °C (2001 to 2025) |
| Cooling degree days | 3,395 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.76 kWh per m² per day |
| Wind at 50 m | 6.1 m/s average |
| Water stress today | Low - Medium (10-20%) (Ceará) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Tecto TFOR3 (ex Mega Lobster) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Subestação Delmiro Gouveia (230 kV), about 8.3 km away.
How clean is the power for Tecto TFOR3 (ex Mega Lobster)?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Who operates Tecto TFOR3 (ex Mega Lobster)?
Tecto Data Centers.
Data centers near Fortaleza
- Cirion Fortaleza 1.7 km
- CSL Monet 2.1 km · 3.4 MW
- Tecto TFOR1/2 (ex Globenet CLS & Big Lobster) 2.6 km
- AngoNAP Fortaleza 2.9 km · 15 MW
- ProveNET - IDC-FLA - Fortaleza 3.1 km
- Giga+ (Alloha Fibra) 5.1 km
- SECRELNET INFORMATICA 6.0 km
- SecrelNet Informática Fortaleza 7.4 km
More Tecto Data Centers data centers
- Tecto TBAQ1/2 (ex Globenet CLS) Colombia
- Tecto TBAQ3 Colombia
- Tecto TFOR1/2 (ex Globenet CLS & Big Lobster) Brazil
- Tecto TGIG1 (ex Globenet CLS RJ) Brazil
- Tecto TGIG2 (ex Arcos) Brazil
Sources
Correct this page or get the data