VERIXI Louise DC
VERIXI Louise DC is an operational data center operated by VERIXI in Brussels, Belgium. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | VERIXI |
| Networks | 5 networks, 1 internet exchanges PeeringDB. |
| Address | Avenue Louise 326 |
| Coordinates | 50.82294, 4.36895 |
| Website | verixi.be/datacenter |
Power and grid
| Nearest high-voltage substation | Dhanis, 150 kV, 2.2 km away (Elia) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Elia Drogenbos, 380 kV, 5.2 km away |
| HV substations within 10 km | 9 |
| Power plants within 50 km | 2.5 GW in 19 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 151 g CO₂ per kWh (Belgium, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 33.5%, gas 20.8%, wind 18.6%, solar 14.5%, oil and other fossil 7.1%. Clean power: 72.1% |
| Industrial power price | EUR 0.133 per kWh (Belgium, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.6 °C (2001 to 2025) |
| Cooling degree days | 87 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.03 kWh per m² per day |
| Wind at 50 m | 6.7 m/s average |
| Water stress today | Extremely High (>80%) (Belgium) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is VERIXI Louise DC to the power grid?
The nearest high-voltage substation in OpenStreetMap is Dhanis (150 kV), about 2.2 km away.
How clean is the power for VERIXI Louise DC?
The grid in Belgium emits about 151 g CO₂ per kWh (2025). Largest sources: nuclear 33.5%, gas 20.8%, wind 18.6%.
Who operates VERIXI Louise DC?
VERIXI.
Data centers near Brussels
- O 1.4 km · 0.9 MW
- Level(3) Brussels 4.9 km · 5.9 MW
- Woluwedal 102 6.4 km
- Proximus Netcenter 6.5 km
- DC Evere 6.6 km
- Penta Infra Brussel BRU01 8.6 km · 2 MW
- brusselsdc 8.8 km · 1.3 MW
- MCI/Verizon Brussels (Diegem) E 9.0 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.