Wifx Data Center Vaud
Wifx Data Center Vaud is an operational data center operated by Wifx in Yverdon-les-Bains, Switzerland. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Wifx |
| Networks | 5 networks PeeringDB. |
| Address | Avenue des Sciences 1 |
| Coordinates | 46.76590, 6.64661 |
| Website | wifx.net/business/wifx-datacenter |
Power and grid
| Nearest high-voltage substation | Yverdon, 132 kV, 1.2 km away (SBB) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Poste de Mathod, 220 kV, 7.1 km away |
| HV substations within 10 km | 3 |
| Power plants within 50 km | 239 MW in 17 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 39 g CO₂ per kWh (Switzerland, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.3%, nuclear 29.9%, solar 12.1%, oil and other fossil 1.9%, bioenergy 1.6%. Clean power: 97.7% |
Climate and water
| Average temperature | 8.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 36.6 °C (2001 to 2025) |
| Cooling degree days | 95 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.43 kWh per m² per day |
| Wind at 50 m | 5.6 m/s average |
| Water stress today | Low (<10%) (Vaud) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Wifx Data Center Vaud to the power grid?
The nearest high-voltage substation in OpenStreetMap is Yverdon (132 kV), about 1.2 km away.
How clean is the power for Wifx Data Center Vaud?
The grid in Switzerland emits about 39 g CO₂ per kWh (2025). Largest sources: hydro 52.3%, nuclear 29.9%, solar 12.1%.
Who operates Wifx Data Center Vaud?
Wifx.
Data centers near Yverdon-les-Bains
- EXA Edge DC Villars-Sainte-Croix 23.6 km
- BrainServe 25.0 km · 12 MW
- Brainserve 25.2 km
- Swisscom Savoie 27.3 km · 1.3 MW
- AlpineDC 27.6 km
- NetaPOP Pontarlier 28.1 km
- High DC 37.1 km
- senseLAN B20 42.2 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.