Aliénor.net is an operational data center operated by Alienor.net in Le Bouscat, France. Our footprint estimate of its power is about 0.6 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Alienor.net |
| Facility power | 0.6 MW (range 0.3 MW to 1 MW) Estimate from building footprint, low confidence. Footprint estimate: about 511 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 260 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 44.87399, -0.59791 |
| Website | groupe-aquitem.fr |
Power and grid
| Grid carbon intensity | 41 g CO₂ per kWh (France, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | nuclear 68.3%, hydro 10.3%, wind 8.8%, solar 5.6%, gas 3%. Clean power: 94.9% |
| Industrial power price | EUR 0.098 per kWh (France, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 13.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.9 °C (2001 to 2025) |
| Cooling degree days | 335 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.72 kWh per m² per day |
| Wind at 50 m | 5.2 m/s average |
| Water stress today | Low - Medium (10-20%) (France) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Aliénor.net use?
We estimate the facility power at about 0.6 MW. Estimate from building footprint, low confidence.
How clean is the power for Aliénor.net?
The grid in France emits about 41 g CO₂ per kWh (2025). Largest sources: nuclear 68.3%, hydro 10.3%, wind 8.8%.
Who operates Aliénor.net?
Alienor.net.
Data centers near Le Bouscat
- Equinix BX1 - Bordeaux 2.6 km · 3.4 MW
- Cogent Bordeaux 3.5 km
- UltraEdge Bordeaux 3.6 km
- SFR Netcenter Bordeaux 3.7 km · 8.7 MW
- TDF Datacenter Bordeaux Bouliac 9.5 km
- EXA Edge DC Bordeaux 11.4 km · 1.3 MW
- Bouygues Télécom data center in Léognan 17.5 km · 1.8 MW
- EXA Edge DC Ychoux 66.3 km
Sources
Correct this page or get the data