CENTURY TELECOM LTDA
CENTURY TELECOM LTDA is an operational data center operated by CENTURY TELECOM in Belo Horizonte, Brazil. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | CENTURY TELECOM |
| Networks | 6 networks PeeringDB. |
| Address | Rua Tenente garro, 118, 14 Andar |
| Coordinates | -19.92617, -43.91842 |
| Website | century.net.br |
Power and grid
| Nearest high-voltage substation | Subestação Santa Efigênia, 138 kV, 600 m away (Cemig) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Subestação Taquaril, 345 kV, 7 km away |
| HV substations within 10 km | 12 |
| Grid carbon intensity | 109 g CO₂ per kWh (Brazil, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.1%, wind 15.2%, solar 11.5%, bioenergy 8.1%, gas 7.8%. Clean power: 88.9% |
Climate and water
| Average temperature | 20.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.7 °C (2001 to 2025) |
| Cooling degree days | 1,000 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.02 kWh per m² per day |
| Wind at 50 m | 4.9 m/s average |
| Water stress today | Low (<10%) (Minas Gerais) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is CENTURY TELECOM LTDA to the power grid?
The nearest high-voltage substation in OpenStreetMap is Subestação Santa Efigênia (138 kV), about 600 m away.
How clean is the power for CENTURY TELECOM LTDA?
The grid in Brazil emits about 109 g CO₂ per kWh (2025). Largest sources: hydro 52.1%, wind 15.2%, solar 11.5%.
Who operates CENTURY TELECOM LTDA?
CENTURY TELECOM.
Data centers near Belo Horizonte
- MASTER DA WEB 1.7 km
- PIX Vogel Telecom BH 1.9 km
- PIX Prodabel 2.1 km
- G8 Teleporto Serra do Curral Belo Horizonte 2.3 km
- MGcloud 3.8 km
- Data Center (Ministério Público de Minas Gerais) 6.3 km · 0.9 MW
- PoP-MG 7.9 km
- PIX Sempre (Brasil TecPar) 11.1 km
More CENTURY TELECOM data centers
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.