Data Center Directory

Cibicom Datacenter Aarhus

Cibicom Datacenter Aarhus is an operational data center operated by Cibicom A/S in Højbjerg, Denmark. No power figure is public for this site yet.

Key facts

StatusOperational
OperatorCibicom A/S
Networks2 networks
PeeringDB.
AddressNy Moesgårdvej 61
Coordinates56.09904, 10.21722
Websitecibicom.dk

Power and grid

Nearest high-voltage substation150 kV Høskov, 150 kV, 5.6 km away
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substation400/150 kV Malling, 400 kV, 7.5 km away
HV substations within 10 km3
Power plants within 50 km954 MW in 11 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity120 g CO₂ per kWh (Denmark, 2025)
Average of all power made in the area. Ember.
Grid power mixwind 56.9%, bioenergy 21.4%, solar 12.8%, oil and other fossil 4.9%, coal 2.5%. Clean power: 91.2%
Industrial power priceEUR 0.118 per kWh (Denmark, 2026-S1)
Non-household users with 20 to 70 GWh per year, without VAT. Eurostat.

Climate and water

Average temperature8.5 °C
NASA POWER, average of 2001 to 2025.
Highest temperature27.6 °C (2001 to 2025)
Cooling degree days23 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy2.84 kWh per m² per day
Wind at 50 m7.6 m/s average
Water stress todayLow (<10%) (Denmark)
Share of the local water supply that people already use. WRI Aqueduct 4.0, country level.
Water stress in 2050Low (<10%)
Business-as-usual scenario.

Satellite view

Questions

How close is Cibicom Datacenter Aarhus to the power grid?

The nearest high-voltage substation in OpenStreetMap is 150 kV Høskov (150 kV), about 5.6 km away.

How clean is the power for Cibicom Datacenter Aarhus?

The grid in Denmark emits about 120 g CO₂ per kWh (2025). Largest sources: wind 56.9%, bioenergy 21.4%, solar 12.8%.

Who operates Cibicom Datacenter Aarhus?

Cibicom A/S.

Data centers near Højbjerg

More Cibicom A/S data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.