Cibicom Datacenter Aarhus North
Cibicom Datacenter Aarhus North is an operational data center operated by Cibicom A/S in Hinnerup, Denmark. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Cibicom A/S |
| Address | Kappa 10 |
| Coordinates | 56.23846, 10.11419 |
| Website | cibicom.dk |
Power and grid
| Nearest high-voltage substation | 400/220/150 kV Trige, 400 kV, 4.3 km away (Energinet) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 3 |
| Power plants within 50 km | 1.0 GW in 13 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 120 g CO₂ per kWh (Denmark, 2025) Average of all power made in the area. Ember. |
| Grid power mix | wind 56.9%, bioenergy 21.4%, solar 12.8%, oil and other fossil 4.9%, coal 2.5%. Clean power: 91.2% |
| Industrial power price | EUR 0.118 per kWh (Denmark, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 8.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 27.6 °C (2001 to 2025) |
| Cooling degree days | 23 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.84 kWh per m² per day |
| Wind at 50 m | 7.6 m/s average |
| Water stress today | Low (<10%) (Denmark) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Cibicom Datacenter Aarhus North to the power grid?
The nearest high-voltage substation in OpenStreetMap is 400/220/150 kV Trige (400 kV), about 4.3 km away.
How clean is the power for Cibicom Datacenter Aarhus North?
The grid in Denmark emits about 120 g CO₂ per kWh (2025). Largest sources: wind 56.9%, bioenergy 21.4%, solar 12.8%.
Who operates Cibicom Datacenter Aarhus North?
Cibicom A/S.
Data centers near Hinnerup
- Fuzion Aarhus 10.0 km
- Kolo DK4 Viby J. 13.7 km
- Cibicom Datacenter Aarhus 16.8 km
- GlobalConnect Hørning 2 18.9 km
- Fuzion Skanderborg 20.2 km
- GlobalConnect Stilling 20.6 km
- Novo Nordisk Gefion 30.9 km · 2.9 MW
- Apple data center in Viborg 43.0 km · 57 MW
More Cibicom A/S data centers
- Cibicom Datacenter Aarhus Denmark
- Cibicom Datacenter Ballerup Denmark
- Cibicom Datacenter CPH West Denmark
- Cibicom Taulov Denmark
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.