Digital Edge PUS1 - Busan
Digital Edge PUS1 - Busan is an operational data center operated by Digital Edge DC in Haeundae-gu, South Korea. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Digital Edge DC |
| Address | 32, Centum 7-ro |
| Coordinates | 35.17491, 129.12743 |
| Website | digitaledgedc.com/products/datacenters/south-korea#pus1 |
Power and grid
| Nearest high-voltage substation | 수영변전소, 154 kV, 700 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | 동부산변전소, 345 kV, 4.3 km away |
| HV substations within 10 km | 8 |
| Power plants within 50 km | 17 GW in 16 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 418 g CO₂ per kWh (South Korea, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 31.1%, nuclear 29.4%, gas 28%, solar 6%, bioenergy 3.2%. Clean power: 39.9% |
Climate and water
| Average temperature | 14.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.5 °C (2001 to 2025) |
| Cooling degree days | 641 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.9 kWh per m² per day |
| Wind at 50 m | 6.1 m/s average |
| Water stress today | Medium - High (20-40%) (Busan) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Digital Edge PUS1 - Busan to the power grid?
The nearest high-voltage substation in OpenStreetMap is 수영변전소 (154 kV), about 700 m away.
How clean is the power for Digital Edge PUS1 - Busan?
The grid in South Korea emits about 418 g CO₂ per kWh (2025). Largest sources: coal 31.1%, nuclear 29.4%, gas 28%.
Who operates Digital Edge PUS1 - Busan?
Digital Edge DC.
Data centers near Haeundae-gu
- kt cloud Songjeong GHC 6.3 km
- Data center in Kimhae 25.4 km · 7 MW
- Data center in Geoje 62.6 km · 4.2 MW
- 국가정보자원관리원 대구센터 96.1 km · 28 MW
More Digital Edge DC data centers
- Digital Edge OSA2 Japan
- Digital Edge TYO2 (ComSpace 1) - Tokyo Japan
- Digital Edge BOM1 India
- DIgital Edge CGK Campus Indonesia
- Digital Edge MNL1 (NARRA1) - Manila Philippines
- Digital Edge OSA1 - Osaka Japan
- Digital Edge SEL1 - Seoul South Korea
- Digital Edge SEL2 SEL3 - Seoul South Korea
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.