eBay
eBay is an operational data center in Herriman, United States. Our footprint estimate of its power is about 33 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 33 MW (range 16 MW to 52 MW) Estimate from building footprint, low confidence. Footprint estimate: about 27,182 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 14,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 40.56360, -112.04780 |
Power and grid
| Utility | Pacificorp (investor owned) Electric retail service territory (HIFLD, US government). |
|---|---|
| Balancing authority | PACW, PACE |
| Nearest gas pipeline | Kern River Gas Trans Co, interstate pipeline, 2.1 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Grid carbon intensity | 200 g CO₂ per kWh (Oregon, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 44.6%, gas 33.9%, wind 14.5%, solar 5.2%, bioenergy 1.6%. Clean power: 66.2% |
| Industrial power price | USD 0.087 per kWh (Oregon, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 9.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.1 °C (2001 to 2025) |
| Cooling degree days | 469 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.8 kWh per m² per day |
| Wind at 50 m | 3.7 m/s average |
| Water stress today | Low - Medium (10-20%) (Oregon) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does eBay use?
We estimate the facility power at about 33 MW. Estimate from building footprint, low confidence.
How clean is the power for eBay?
The grid in Oregon emits about 200 g CO₂ per kWh (2025). Largest sources: hydro 44.6%, gas 33.9%, wind 14.5%.
Data centers near Herriman
- Ebay 246 m · 14 MW
- Aligned Salt Lake (SLC-02) 7.0 km
- Flexential - Salt Lake City/South Valley (SLC09) 8.3 km · 2.6 MW
- Verizon 12.5 km · 1.3 MW
- FIBERSTATE Salt Lake City (SLC1) 14.7 km · 0.9 MW
- DataBank Salt Lake City (SLC2) 15.3 km · 21 MW
- Senawave 17.9 km
- EdgeConneX Salt Lake City (EDCSLC01) 18.3 km