Epic / Mayo Data Center
Epic / Mayo Data Center is an operational data center in Rochester, United States. Our footprint estimate of its power is about 6.9 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 6.9 MW (range 3.5 MW to 11 MW) Estimate from building footprint, low confidence. Footprint estimate: about 5,772 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 2,900 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | West Circle Drive NW 4710, 55901, Rochester |
| Coordinates | 44.07080, -92.52213 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 161 kV, 200 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Byron Substation, 345 kV, 12.4 km away |
| HV substations within 10 km | 11 |
| Utility | Rochester Public Utilities (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | MISO |
| Nearest gas pipeline | Northern Natural Gas Co, interstate pipeline, 5.3 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 742 MW in 54 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 344 g CO₂ per kWh (Minnesota, 2025) Average of all power made in the area. Ember. |
| Grid power mix | wind 25.1%, coal 23%, nuclear 21.5%, gas 20.7%, solar 5.9%. Clean power: 55.8% |
| Industrial power price | USD 0.100 per kWh (Minnesota, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 7.2 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.6 °C (2001 to 2025) |
| Cooling degree days | 312 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.85 kWh per m² per day |
| Wind at 50 m | 7.1 m/s average |
| Water stress today | Medium - High (20-40%) (Minnesota) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Epic / Mayo Data Center use?
We estimate the facility power at about 6.9 MW. Estimate from building footprint, low confidence.
How close is Epic / Mayo Data Center to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (161 kV), about 200 m away. The local utility is Rochester Public Utilities, in the MISO balancing area.
How clean is the power for Epic / Mayo Data Center?
The grid in Minnesota emits about 344 g CO₂ per kWh (2025). Largest sources: wind 25.1%, coal 23%, nuclear 21.5%.
Data centers near Rochester
- NP Rochester 7.3 km
- Project Skyway 19.1 km · 94 MW
- Jaguar Communications 56.4 km
- SFN MN-Albert Lea 84.5 km
- Meta Rosemount Data Center 85.4 km · 88 MW
- Meta Rosemount 88.5 km · 241 MW
- DataBank Minneapolis (MSP2) 98.7 km
- Verizon - Bloomington Network 106.3 km · 7.4 MW
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.